HomeMy WebLinkAbout2022-096 CCR Member Graves introduced the following resolution and
moved its adoption:
RESOLUTION NO. 2022-96
RESOLUTION APPROVING CHANGE ORDER NOS. 13-16,
IMPROVEMENT PROJECT NO. 2021-05, BROOKLYN BOULEVARD
CORRIDOR PROJECT PHASE 2 IMPROVEMENTS
, WHEREAS,pursuant to a written contract signed with the City of Brooklyn !
Center, Minnesota, Park Construction Company of Minneapolis, Minnesota, was instructed to �
complete additional work as itemized on Change Order Nos. 13-16 for Improvement Project No. '
2021-05, Brooklyn Boulevard Corridor Project Phase 2 Improvements; and �
WHEREAS, Change Order 13 in the amount of $71,389.38 is for replacing
existing watermain gate valves adjacent to the project area that were determined not to be
functional and for additional hydrant extensions within the project area. This included
� replacement of gate valves adjacent to Brooklyn Blvd at the Fire Station south of 63rd Ave, at
63rd Ave, 65th Ave, and Halifax Dr. Additionally, hydrant extensions were needed due to
differences in existing watermain depths than standard along Brooklyn Blvd at 61 st Ave and
62nd Ave; and
WHEREAS, Change Order 14 in the amount of$13,850.00 is for installation of
new concrete footings for the salvaged ornamental fence in the northwest corner of Brooklyn
Blvd and 63th Ave; and
WHEREAS, Change Order 15 in the amount of $2,930.00 is for directionally
boring a 4-inch and 1.5-inch conduit crossings under NB Brooklyn Blvd for the median
irrigation system north of 65th Avenue; and
WHEREAS, Change Order 16 in the amount of $70,750.00 is for providing a
� temporary vertical shoring system to safely construct the underground stormwater storage
chamber (Const Drainage Structure Design Spec 2) in the northwest corner of Brooklyn
Boulevard and 63rd Avenue.; and
WHEREAS, said additional work was not included in the original contract, but
was deemed necessary to properly complete the improvements.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brooklyn Center, Minnesota,that Change Order Nos. 13 through 15 in the amount of$88,169.38
for Improvement No. 2021-OS is hereby approved. The revised contract amount is as follows:
Ori inal C�ntract Amount $12,222,880.30
g
Change Order Nos. 1-7 $ 48,117.21
Change Order Nos. 8-12 $ 14,011.21
Chan�e Order Nos. 13-16 $ 158,919.38
Revised Contract Amount $12,443,928.10
RESOLUTION NO. 2022-96
�
September 26, 2022 i�
� Date Mayor
ATTEST:
City Cler
The motion for the adoption of the foregoing resolution was duly seconded by member Lawrence-Anderson
and upon vote being taken thereon, the following voted in favor thereof: Graves, Lawrence-Anderson, Ryan
and Elliott
and the following voted against the same: None
whereupon said resolution was declared duly passed and adopted.