HomeMy WebLinkAbout1996-015 CCR1
1
adoption:
Member Kathleen Carmody introduced the following resolution and moved its
RESOLUTION NO. 96 -15
RESOLUTION APPROVING CHANGE ORDER #1, IMPROVEMENT PROJECT NOS. 1995-
07, 08 AND 09, CONTRACT 1995 -B, WOODBINE AREA STREET, STORM DRAINAGE
AND UTILITY IMPROVEMENTS
WHEREAS, due to conditions unknown at the time of plan preparation, the items shown
on attached Change Order #1 have been completed by Thomas Sons Construction.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Brooklyn
Center, Minnesota that:
1.
2.
Change Order #1 is hereby approved.
The work completed under said contract is accepted and approved according to
the following schedule:
As Amended
Estimated Proiect Costs Per Low 13k1
Contract $1,454,565.57
Contingency (10
Change Order #1
Sub -Total Construction
Admin, Engr. Legal (13%)
Est. Total Project Cost
Estimated Project Revenues,
Special Assessments
G.O. Bonds
MSA (State Aid)
Storm Drainage Utility Fund
Public Utility Fund
Sanitary
Water
145,456.56
$1,600,022.13
208.002.8$
$1,808,025.01
As Amended
per Low Bid
$589,500.00
744,813.96
75,740.05
202,618.00
$195.351.00
145,300.00
60,053.00
Total Est. Project Revenue $1,808,025.01
As Amended
Change Order #1
$1,454,565.57
(8%) 116,681.21
(2%) 28.775.35
1,600,022.13
208.002.88
$1,808,025.01
As Amended
Change Order
$589,500.00
727,312.56
75,740.05
217,792.64
$197.652.37
142,624.98
55,027.39
$1,808,025.01