HomeMy WebLinkAbout1995-231 CCR1 Member Kathleen Carmody introduced the following resolution and moved its adoption: RESOLUTION NO. 95 231 RESOLUTION APPROVING CHANGE ORDER #2, ACCEPTING WORK PERFORMED AND APPROVING FINAL PAYMENT, IMPROVEMENT PROJECT NO. 1994 -19, CONTRACT 1994 -J, SHINGLE CREEK PARKWAY MILL AND OVERLAY WHEREAS, pursuant to written contract signed with the City of Brooklyn Center, Minnesota, Northwest Asphalt has satisfactorily completed the following improvement in accordance with said contract: Improvement Project No. 1994 -19, Contract 1994 -J, Shingle Creek Parkway Mill and Overlay NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Brooklyn Center, Minnesota that: 1. Change Order #2 is hereby approved. 2. The work completed under said contract is accepted and approved according to the following schedule: Est. Project Costs Contract Contingency Subtotal Supplemental Agree. #1 Change Order #1 Change Order #2 Subtotal Construction Engineering Admin /Legal Total Est. Project Cost As Amended Per Low Bid $257,037.75 25. 703.25 (10 $282,741.00 28,274.00 8.482.23 $319,497.23 As Amended Per Supp. Agreement #1 Chan ge Order #1& #2 As Final $257,037.75 19,963.40 (5%) $277,001.15 69,859.86 36,545.50 35.824.89 $419,231.14 28,274.00 12.579.94 $460,085.08 $292,040.89 $292,040.89 69,859.86 36,545.50 35.824.89 434,271.14 19,990.76 13.028.13 $467,290.03 1 1 RESOLUTION NO. 95 -231 ATTEST: Est. Proiect Revenues Special Assessments (MCTO Contribution) Regular Municipal State Aid Fund 1496 Local Municipal State Aid Fund 2911 Water Utility Sanitary Sewer Utility Storm Drainage Utility Total Estimated Project Revenue October 23, 1995 Date As Amended Per Low Bid $188,550.00 253,240.00 (158,963.00) 2,740.00 4,410.00 29.520.00 $319,497.00 As Amended Per Supp. Agreement #1 Change Order #1 &2 $188,550.00 372,979.39 (138,114.31) 2,740.00 4,410.00 29.520.00 $460,085.08 3. The actual value of the work performed is $8,533.04 more than the original contract plus approved Change Order No. 1 2 and Supplemental Agreement No. 1. 4. It is hereby directed that final payment be made on said contract, taking the Contractor's receipt in full. The total amount to be paid for said improvement under said contract shall be $398,739.20. Maor As Final $166,137.14 16,000.00 386,302.23 (137,819.34) 2,740.00 4,410.00 29.520.00 $467,290.03 The motion for the adoption of the foregoing resolution was duly seconded by member Debra Hilstrom and upon vote being taken thereon, the following voted in favor thereof: Myrna Kragness, Kristen Mann, Debra Hilstrom, and Kathleen Carmody; and the following voted against the same: none, whereupon said resolution was declared duly passed and adopted.