Member Celia Scott introduced the following resolution and
moved its adoption:
RESOLUTION NO. 93 -196
RESOLUTION ACCEPTING WORK PERFORMED AND APPROVING FINAL
PAYMENT FOR CONTRACT 1993 -C, REPLACEMENT OF WATER MAINS ON
LAWRENCE ROAD AND ALDRICH COURT, IMPROVEMENT PROJECT NO.
1993 -07, AND SANITARY SEWER REPAIR (5 LOCATIONS),
IMPROVEMENT PROJECT NO. 1993 -16
WHEREAS, pursuant to written contract signed with the City of
Brooklyn Center, Minnesota, Metro Utilities, Inc. has satisfactorily completed
the following improvement in accordance with said contract:
REPLACEMENT OF WATER MAINS ON LAWRENCE ROAD AND ALDRICH COURT,
IMPROVEMENT PROJECT NO. 1993 -07, AND SANITARY SEWER REPAIR (5
LOCATIONS), IMPROVEMENT PROJECT NO. 1993 -16
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of
Brooklyn Center, Minnesota, that:
1. The work completed under said contract is accepted and approved
according to the following schedule:
As Bid
As Amended
Per Approved
Chance Orders
Final Amount
Original Contract $54,333.00 $57,861.20 $58,725.11
2. The actual value of work performed is $863.91 more than the original
contract value plus approved change order, due to a minor
underestimation of quantities.
3. It is hereby directed that final payment be made on said contract,
taking the Contractor's receipt in full. The total amount to be paid
for said improvement under said contract shall be $58,725.11.
4. The project costs for Improvement Project No. 1993 -07, Replacement of
Water Mains on Lawrence Road and Aldrich Court, are amended according
to the following schedule:
1
1
RESOLUTION NO. 93 -196
As Amended
Per Bid
and Approved
As Established Change Order Final
Contract $41,253 $41,433.00 $42,296.91
Contingency 6.188 4.143.00 -0-
Subtotal Construction $47,441 $45,576.00 $42,296.91
Staff Engineering (10%) 4,744 4,558.00 4,229.69
Admin. Legal (3 1.423 1.367.00 1.268.91
Total Est. Project Cost $53,608 $51,501.00 $47,795.51
Improvement Project 1993 -07
5. The project costs for Improvement Project No. 1993 -16, Sanitary Sewer
Repairs (Southeast Neighborhood) are amended to the following
schedule:
As Amended
Per Bid
and Approved
As Established Change Order Final
Contract $30,100 $16,428.20 $16,428.20
Contingency 4.515 821.41 -0-
Subtotal Construction $34,615 $17,249.61 $16,428.20
Staff Engineering (10 3,462 1,724.96 1,642.82
Admin. Legal (3J) 1.038 517.49 492.85
Total Est. Project Cost $39,115 $19,492.06 $18,563.87
Improvement Project 1993 -16
November 8, 1993
Date Todd Paulson, Mayor
ATTEST:
Deputy Clerk
The motion for the adoption of the foregoing resolution was duly seconded by
member Barb Kalligher and upon vote being taken thereon, the
following voted in favor thereof:
Todd Paulson, Celia Scott, Dave Rosene, and Barb Kalligher;
and the following voted against the same: none,
whereupon said resolution was declared duly passed and adopted.