Member Celia Scott introduced the following resolution and
moved its adoption:
RESOLUTION NO. 93 -111
RESOLUTION ACCEPTING BID AND AWARDING CONTRACT FOR SANITARY
SEWER REPAIRS (SOUTHEAST NEIGHBORHOOD), IMPROVEMENT PROJECT NO.
1993 -16 AND WATER MAIN REPLACEMENT (LAWRENCE ROAD AND
ALDRICH COURT), IMPROVEMENT PROJECT NO. 1993 -07, CONTRACT 1993 -C
WHEREAS, pursuant to an advertisement for bids for Contract 1993 -C,
bids were received, opened, and tabulated by the City Engineer, on the 7th day
of July, 1993. Said bids were as follows:
Bidder Bid Amount
Metro Utilities
Thomas Sons, Inc.
Dave Perkins Contracting
W. B. Miller, Inc.
Volk Sewer Water
Bonine Excavating, Inc.
54,333.00
64,311.40
70,759.00
73,265.50
90,398.50
$105,662.90
WHEREAS, it appears that Metro Utilities, Inc., of Plymouth,
Minnesota, is the lowest responsible bidder.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of
Brooklyn Center, Minnesota, that:
1. The Mayor and City Manager are hereby authorized and directed to
enter into a contract in the amount of $54,333.00, with Metro
Utilities, Inc., of Maple Grove, Minnesota in the name of the City of
Brooklyn Center, for Contract 1993 -C according to the plans and
specifications approved by the City Council and on file in the office
of the Deputy City Clerk.
2. The Deputy City Clerk is hereby authorized and directed to return
forthwith to all the bidders the deposits made with their bids,
except that the deposit of the successful bidder and the next lowest
bidder shall be retained until a contract has been signed.
3. The estimated costs for Improvement Project No. 1993 -07, Replacement
of Water Mains on Lawrence Road and on Aldrich Court, are amended as
follows:
1
1
ATTEST:
RESOLUTION No. 93 -111
Contract $41,253 $41,433.00
Contingency 6.188 4.143.00
Subtotal Construction $47,441 $45,576.00
Staff Engineering (107.) 4,744 4,558.00
Admin. Legal (37.) 1.423 1.367.00
Total Est. Project Cost $53,608 $51,501.00
Improvement Project 1993 -07
4. The estimated costs for Improvement Project No. 1993 -16, Sanitary
Sewer Repairs (Southeast Neighborhood) are amended as follows:
Contract $30,100 $12,900.00
Contingency 4.515 1.290.00
Subtotal Construction $34,615 $14,190.00
Staff Engineering (10 3,462
Admin. Legal (37.)
Total Est. Project Cost $39,115
Improvement Project 1993 -16
July 12, 1993
Date
U K,rr Q
Deputy Clerk
As Amended
As Established Per Low Bid
As Established
1.038
Todd Mayor
As Amended
Per Low Bid
1,419.00
426.00
$16,035.00
The motion for the adoption of the foregoing resolution was duly seconded by
member Dave Rosene and upon vote being taken thereon, the
following voted in favor thereof:
Todd Paulson, Celia Scott, Dave Rosene, Barb Kalligher, and Kristen Mann;
and the following voted against the same: none,
whereupon said resolution was declared duly passed and adopted.