HomeMy WebLinkAbout1992-286 CCR1
Member Philip Cohen introduced the following resolution and
moved its adoption:
PART I ROADWAY COSTS
A. STREET CONSTRUCTION COSTS
"NOTE: Cost is estimated at this time
RESOLUTION NO. 92 286
RESOLUTION APPROVING REVISED PROJECT COST ESTIMATES
WHEREAS, City Council resolution number 90 -66 ordered improvement
project 1990 -10, the reconstruction of 69th Avenue North from Noble Avenue
North to Shingle Creek Parkway; and
WHEREAS, resolution number 91 -160 estimated the total cost of the
project as of June, 1991 to be $7,669,780; and
WHEREAS, more detailed information now available allows for a more
realistic estimate of cost.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of
Brooklyn Center, Minnesota, that the estimated cost of improvement project
number 1990 -10 is hereby amended according to the folowing schedule:
June, 1991 As Approved
EStimatp Or Estimated
December, 1992
Estimate
Roadway construction, including storm $2,528,400 $2,299,977 $2,273,000
surcharge, basic landscaping, wetland
mitigation, and compensating storage
PHASE l Soil Correction and Wet /and 732,607 675,000
PHASE 1/ Road Construction 917,370 948,000
PHASE 111- Road in Palmer Lake Area 650,000 650,000
Special landscaping and fencing 200,000 210,000 210,000
Phase 1 20,000
Phase 11 164,600
Phase 111 25,400
Traffic signals at France Avenue 95,000 80,500 80,500
Private utility relocation and street lighting 350,000 258,109 258,109
Irrigation system N/I 80,000 131,000
SUBTOTAL, CONSTRUCTION COSTS $3,173,400 $2,928,586 $2,952,609
1
1
RESOLUTION NO. 92 -286
B. ENGINEERING AND OTHER COSTS
RELATING TO STREET IMPROVEMENTS $708,900 $788,870 $945,788
Consultant costs design 280,000 324,290 400,900
Project concept 195,000 184,200
Phase 1 33,100 35,000
Phase 11 81,290 127,000
Phase III N/I 8,800
Landscaping Phase 1 14,900 34,900
Landscaping Phase II N/I 11,000
Consultant costs construction 230,000 265,680 336,990
Phase 1 124,850 134,500
Phase II 103,830 80,490
Phase III N/I 85,000
Landscaping Phase 1 32,000 32,000
Landscaping Phase II 5,000 5,000
Staff costs engineering (2 56,500 56,500 59,100
Legal and administrative costs (2 56,500 56,500 59,100
Testing, etc. (1 -1/2 37,900 37,900 20,000
Bonding costs 28,000 28,000 59,466
Archaeological services 20,000 20,000 10,232
SUBTOTAL, ENGINEERING COSTS $708,900 $788,870 $945,788
C. RIGHT OF WAY ACQUISITION $2,585,380 $2,577,381 $2,551,042
Direct Payments to Owners
a. Acquisition 2,000,000 2,000,000 1,993,103
Residential 1,778,103
Commercial 215,000
b. Relocation 500,000 500,000 440,270
Residential 339,360
Commercial 100,910
Professional Services 156,000 156,000 202,232
a. Evergreen Land Services (Acquisitions) 80,000 80,000 70,305
b. Conworth Inc (Relocation) 40,000 40,000 39,508
c. Holmes and Graven (Legal) 30,000 30,000 52,032
d. Maintenance Security 6,000 6,000 8,635
e. Appraisals N/I 15,013
f. Board of Commissioners (Condemnation) N/I 16,740
Building Demolition 20,000 15,271 15,271
Building Resale
1
1
1
RESOLUTION NO. 92 -286
Other Costs 39,380 42,373 36,429
a. Taxes Titles 24,380 27,373 27,373
b. Miscellaneous (Utilities, Survey, Testing, 15,000 15,000 9,056
NET SUBTOTAL, RIGHT OF WAY COSTS
D. CONTINGENCY
GRAND TOTAL, ROADWAY COSTS
REVENUE SUMMARY: ROADWAY
MSA #1496
MSA #1496/2911
MSA #2911
MSA #2900
MSA #2912 (Bonds)
Water Utility Fund
Sanitary Sewer Utility Fund
Storm Drainage Utility Fund
Hennepin County
Special Assessments
PART II CITY UTILITY IMPROVEMENTS
A. WATER MAIN IMPROVEMENTS
B. SANITARY SEWER IMPROVEMENTS
$2,585,380
388,200
$6,855,880
$3,750,880
2,955,000
150,000
$6,855,880
$2,577,381 $2,551,042
388,200 389,840
$6,683,037 $6,839,280
$2,357,572
$3,471,892
592,924
677,639
3,000,000 3,000,000
550 550
200 200
4,520 4,520
55,875 55,875
150,000 150,000
$6,683,037 $6,839,280
Construction costs $304,700 $329,000 $329,000
PHASE 11 $252,000 252,000
PHASE /l/ 77,000 77,000
Consultant costs engineering 48,400 33,490 32,850
Staff costs engineering (2 6,100 6,600 6,600
Legal and administrative costs (2 6,100 6,600 6,600
SUBTOTAL, WATER $365,300 $375,690 $375,050
Construction costs $285,400 $285,400 8315,000
Consultant costs engineering 45,600 30,140 30,660
Staff costs engineering (2 5,700 5,700 6,300
Legal and administrative costs (2 5,700 5,700 6,300
SUBTOTAL, SANITARY SEWER $342,400 $326,940 $358,260
1
1
RESOLUTION NO. 92 -286
I C. CONTINGENCY
GRAND TOTAL, UTILITY COSTS
REVENUE SUMMARY: UTILITIES
Water Utility Fund
Sanitary Sewer Utility Fund
December 14, 1992
Date
ATTEST:
Deputy Clerk
106,200
$813,900
$813,900
GRAND TOTAL PROJECT COSTS.
ROAD AND PUBLIC UTILITES $7,669,780
420,100 432,040 412,555
393,800 375,980 394,085
$7,491,057 $7,645,920
Toddlaulson, Mayor
105,390 73,330
$808,020 $806,640
$808,020 $806,640
The motion for the adoption of the foregoing resolution was duly seconded by
member Celia Scott and upon vote being taken thereon, the
following voted in favor thereof:
Todd Paulson, Celia Scott, Jerry Pedlar, Dave Rosene, and Philip Cohen;
and the following voted against the same: none,
whereupon said resolution was declared duly passed and adopted.