Loading...
HomeMy WebLinkAbout1992-159 CCR1 1 1 Member Celia Scott introduced the following resolution and moved its adoption: ATTEST: RESOLUTION NO. 92 -159 RESOLUTION ACCEPTING WORK PERFORMED AND APPROVING FINAL PAYMENT FOR TRUNK SEWER REPLACEMENT UNDER 194/694, IMPROVEMENT PROJECT NO. 1992 -03, CONTRACT 1992 -D WHEREAS, pursuant to written contract signed with the City of Brooklyn Center, Minnesota, Barbarossa and Sons, Inc. has satisfactorily completed the following improvement in accordance with said contract: TRUNK SEWER REPLACEMENT UNDER 194/694 IMPROVEMENT PROJECT NO. 1992 -03 NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of Brooklyn Center, Minnesota, that: 1. The work completed under said contract is accepted and approved according to the following schedule: Per Low Bid and Approved Change Order As Final Contract $201,159.38 $200,120.40 Staff Engineering (8%) 16,092.75 16,009.63 Admin. Legal (2 4,023.19 4.002.41 Total Est. Project Cost $221,275.32 $220,132.44 2. The actual value of work performed is $1,038.98 less than the original contract, plus approved Change Order due to an overestimation of quantities. 3. It is hereby directed that final payment be made on said contract, taking the Contractor's receipt in full. The total amount to be paid for said improvement under said contract shall be $200,120.40. July 13, 1992 Date Deputy Clerk Todd Paulson,`-Mayor The motion for the adoption of the foregoing resolution was duly seconded by member Dave Rosene and upon vote being taken thereon, the following voted in favor thereof: Todd Paulson, Celia Scott, Dave Rosene, and Philip Cohen; and the following voted against the same: none, whereupon said resolution was declared duly passed and adopted.