Member Celia Scott introduced the following resolution and
moved its adoption:
RESOLUTION NO. 92 -160
RESOLUTION ACCEPTING WORK PERFORMED AND APPROVING FINAL
PAYMENT FOR TRUNK SEWER REPLACEMENT IN BROOKDALE AREA,
IMPROVEMENT PROJECT NO. 1992 -04, CONTRACT 1992 -C
WHEREAS, pursuant to written contract signed with the City of
Brooklyn Center, Minnesota, Penn Contracting Inc. has satisfactorily completed
the following improvement in accordance with said contract:
TRUNK SEWER REPLACEMENT IN BROOKDALE AREA
IMPROVEMENT PROJECT NO. 1992 -04
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of
Brooklyn Center, Minnesota, that:
1. The work completed under said contract is accepted and approved
according to the following schedule:
Contract
Subtotal Construction
Staff Engineering (8
Admin. Legal (2%)
Geotechnical Services
Material Testing (1
Total Est. Project Cost
Per Low Bid and
Approved Change Orders
$135,415.70
135,415.70
10,833.26
2,708.31
1,775.00
1.354.16
$152,086.43
As Final
$124,037.38
124,037.38
9,922.99
2,480.75
1,775.00
1.240.37
$139,456.49
2. The actual value of work performed is $11,378.32 less than the
original contract, plus approved change orders due to an
overestimation of quantities.
3. It is hereby directed that final payment be made on said contract,
taking the Contractor's receipt in full. The total amount to be
paid for said improvement under said contract shall be
$124,037.38.
July 13, 1992
Date Todd Paulson;4Iayor
ATTEST:
Deputy Clerk
The motion for the adoption of the foregoing resolution was duly seconded by
member Dave Rosene and upon vote being taken thereon, the
following voted in favor thereof:
Todd Paulson, Celia Scott, Dave Rosene, and Philip Cohen;
and the following voted against the same: none,
whereupon said resolution was declared duly passed and adopted.