Member Dave Rosene introduced the following resolution and
moved its adoption:
RESOLUTION NO. 92
RESOLUTION ACCEPTING BID AND AWARDING CONTRACT FOR TRUNK
SEWER REPLACEMENT UNDER I94/694, IMPROVEMENT PROJECT
NO. 1992 -03, CONTRACT 1992 -D
WHEREAS, pursuant to an advertisement for bids for Improvement
Project No. 1992 -03, bids were received, opened, and tabulated by the City
Engineer on the 2nd day of April, 1992. Said bids were as follows:
Bidder Bid Amount
Barbarossa and Sons, Inc.
EJM Pipe Services
Brown Cris
Lametti Sons
198,831.00
207,685.00
208,700.00
257,856.00
WHEREAS, all bids exceed the City Engineer's contract cost estimate
of 191,110; and
WHEREAS, the Director of Public Works has recommended that the
Council accept the low bid received because (1) this segment of sewer is in
imminent danger of collapse, and that such a collapse could result in major
damage to private properties and additional costs; and (2) he believes these
bids to be competitive and it is in his opinion that the City could not
receive lower bids for this work at this time; and
WHEREAS, it appears that Barbarossa and Sons, Inc. of Osseo,
Minnesota, is the lowest responsible bidder.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of
Brooklyn Center, Minnesota, that:
1. The Mayor and City Manager are hereby authorized and directed to
enter into a contract, in the amount of 198,831.00, with
Barbarossa and Sons, Inc., of Osseo, Minnesota in the name of the
City of Brooklyn Center, for Improvement Project No. 1992 -03
according to the plans and specifications approved by the City
Council and on file in the office of the Deputy City Clerk.
2. The Deputy City Clerk is hereby authorized and directed to return
forthwith to all the bidders the deposits made with their bids,
except that the deposit of the successful bidder and the next
lowest bidder shall be retained until a contract has been signed.
BE IT FURTHER RESOLVED that the estimated cost of Improvement Project
No. 1992 -03 is hereby amended according to the following schedule:
1
ATTEST:
RESOLUTION NO. 92
Subtotal Construction
Staff Engineering (8%)
Admin. Legal (2
Total Estimated Project Cost
April 13, 1992
Date
Deputy Clerk
As Amended Per
As Established Low Bid
Contract 166,180 198,831.00
Contingency 24.930 (15 9.942.00 (5
191,110 208,773.00
15,290
3.820
16,702.00
S 4.175.00
210,220 229,650.00
The motion for the adoption of the foregoing resolution was duly seconded by
member Philip Cohen and upon vote being taken thereon, the
following voted in favor thereof:
Todd Paulson, Dave Rosene, and Philip Cohen;
and the following voted against the same: none,