HomeMy WebLinkAbout1988-046 CCRRESOLUTION NO. 88
Member Celia Scott introduced the following resolution and moved
its adoption:
RESOLUTION ACCEPTING BID AND AWARDING CONTRACT FOR REROOFING
AND INSULATION OF THE CITY GARAGE (IMPROVEMENT PROJECT NO.
1988 -03. CONTRACT 1988 -F1
WHEREAS, pursuant to an advertisement for bids for Improvement Project
No. 1988 -03, bids were received, opened, and tabulated by the City Manager and
Director of Public Works, on the 22nd day of March, 1988. Said bids were as follows:
Bidder Base Bid Alternate 1 Alternate 2
Palmer West Construction
Berwald Roofing
Meyers and Jackson Roofing
McPhillips Roofing
John A. Dalsin
Central Roofing Company
Dalbec Roofing
Curran V. Neilsen
90,200.00 99,650.00 91,550.00
91,915.00 No Bid No Bid
94,040.00 No Bid No Bid
98,690.00 No Bid No Bid
102,380.00 121,800.00 No Bid
103,026.00 No Bid No Bid
112,028.00 127,389.00 No Bid
No Bid 139,800.00 108,500.00
WHEREAS, it appears that Palmer West Construction Company, Inc. of
Minneapolis, Minnesota, is the lowest responsible bidder.
III NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of
Brooklyn Center, Minnesota:
1. The Mayor and City Manager are hereby authorized and directed to
enter into the attached contract, accepting the "Base Bid in the
amount of $90,200.00, with Palmer West Construction Company, Inc.
of Minneapolis, Minnesota in the name of the City of Brooklyn
Center, for Improvement Project No. 1988 -03 according to the plans
and specifications therefor approved by the City Council and on
file in the office of the City Clerk.
2. The City Clerk is hereby authorized and directed to return
forthwith to all bidders the deposits made with their bids, except
that the deposit of the successful bidder and the next lowest
bidder shall be retained until a contract has been signed.
1
1
RESOLUTION NO. 88 -46
ATTEST:
BE IT FURTHER RESOLVED that:
1. The estimated cost of Improvement Project No. 1988 -03 is hereby
amended according to the following schedule:
As Approved As Bid
Contract $110,600.00 90,200.00
Contingency 16,600.00 -0-
Consulting Engineer 8.420.00 8.420.00
Subtotal $135,620.00 98,620.00
Administration (1 -0- 986.00
TOTAL $135,620.00 99,606.00
2. The estimated costs will be financed from Division 19 of the
General Fund as provided by Resolution No. 87 -241.
March 28, 1988
Date
The motion for the adoption of the foregoing resolution was duly seconded by
member Bill Hawes and upon vote being taken thereon, the following
voted in favor thereof: Dean Nyquist, Gene Lhotka, Celia Scott, Bill Hawes,
and Rich Theis;
and the following voted against the same: none,
whereupon said resolution was declared duly passed and adopted.