Member Bill Hawes
moved its adoption:
WHEREAS the City Council entered into contract 1987 -E with 0 P
Contracting, Inc. for the construction of Improvement Project No. 1987 -03; and
WHEREAS, the City Engineer has determined certain modifications need to
be made to the contract to facilitate the construction of the project, said
modifications being the utilization of an alternate supplier to improve the
delivery date for pipe, so as to compensate for the 36 day delay in the project
resulting from the imposition of a temporary restraining order.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of
Brooklyn Center, Minnesota that:
1. Supplemental Agreement No. 1, providing for an increased cost of
$2,082.12 to Contract 1987 -E, is hereby approved.
2. There is appropriated the sum of $2,082.12 for the additional
costs.
3. The appropriation will be financed by the Public Utility Fund.
ATTEST:
RESOLUTION NO. 87 -121
RESOLUTION APPROVING SUPPLEMENTAL AGREEMENT TO CONTRACT
1987 -E BROOKDALE 16" WATERMAIN IMPROVEMENT PROJECT NO.
1987 -03
June 8, 1987
Date May
Clerk
introduced the following resolution and
The motion for the adoption of the foregoing resolution was duly seconded by
member Celia Scott and upon vote being taken thereon, the
following voted in favor thereof: Dean Nyquist, Celia Scott, and Bill Hawes;
and the following voted against the same: Rich Theis,
whereupon said resolution was declared duly passed and adopted.