HomeMy WebLinkAbout1986-116 CCRMember Rich Theis introduced the following resolution and
moved its adoption:
RESOLUTION NO. 86 -116
RESOLUTION ACCEPTING PROPOSALS FOR BOOSTER PUMPS AND FOR
RECONSTRUCTING PUMP VAULTS FOR WATER QUALITY IMPROVEMENT
PROJECT NO. 1986 -18
WHEREAS, the Director of Public Works has received proposals for
furnishing of booster pumps for water quality improvements, submitted bids being
as follows:
Bidder Bid Amount
Tri -State Pump and Control 7,622.00
Keys Well Drilling Company 12,952.68
WHEREAS, the proposal of Tri -State Pump and Control, in the amount of
$7,622.00 is the lowest responsible proposal received and the Director of Public
Works has recommended that a contract be awarded to said firm in that amount;
and
WHEREAS, the Director of Public Works has received proposals for
installation of the booster pump piping valves and other appurtenant facilities,
submitted proposals being as follows:
Bidder Bid Amount
Hank Weidema Excavating 8,540.00
0 P Contracting, Inc. 21,500.00
Kirkwold Construction 26,500.00
WHEREAS, the proposal of Hank Weidema Excavating, in the amount of
$8,540.00 is the lowest responsible proposal received and the Director of Public
Works has recommended that a contract be awarded to said firm in that amount:
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of
Brooklyn Center, Minnesota:
1. The following project is hereby established:
WATER QUALITY IMPROVEMENT PROJECT NO. 1986 -18
(WATER QUALITY IMPROVEMENTS IN AN AREA BOUNDED BY 65TH AVENUE NORTH
AND 63RD AVENUE NORTH WEST OF NOBLE AVENUE NORTH)
2. The costs for Project No. 1986 -18 are estimated as follows:
Contract Cost (Piping) 2,733.17
Contract Cost (Booster Pumps) 7,622.00
Contract Cost (Manholes Castings) 1,268.90
Contract Cost (Installation) 8.540.00
Subtotal $20,163.17
Engineering Costs (6%) 1.206.83
TOTAL $21,370.00
RESOLUTION NO. 86 -116
3. The proposal of Tri -State Pump and Control, in the amount of
$7,622.00, is hereby accepted. The City Manager is hereby
authorized and directed to enter into a contract with said firm in
that amount.
4. The proposal of Hank Weidema Excavating, in the amount of
$8,540.00, is hereby accepted. The City Manager is hereby
authorized and directed to enter into a contract with said firm in
that amount.
5. Payment for work completed under the contracts above shall be
charged to Public Utilities Fund.
July 28, 1986 i%1 f'�,,�'•
Date Mayor
I
ATTEST:,
Clerk
The motion for the adoption of the foregoing resolution was duly seconded by
member Celia Scott and upon vote being taken thereon, the following
voted in favor thereof: Dean Nyquist, Celia Scott, Bill Hawes, andRich Theis;
and the following voted against the same: none,
whereupon said resolution was declared duly passed and adopted.