HomeMy WebLinkAbout1984-139 CCRMember Bill Hawes introduced the following resolution and
moved its adoption:
RESOLUTION NO. 84 -139
RESOLUTION ACCEPTING WORK PERFORMED UNDER CONTRACT 1984 -H
(SEAL COATING IMPROVEMENT PROJECT NO. 1984 -13)
WHEREAS, pursuant to written Contract 1984 -H signed with the City of
Brooklyn Center, Minnesota, Allied Blacktop Company has satisfactorily completed
the following improvement in accordance with said contract:
SEAL COAT IMPROVEMENT PROJECT NO. 1984 -13
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of
Brooklyn Center, Minnesota, that:
1. The work completed under said contract is accepted and approved
according to the following schedule:
As Approved Final Amount
Original Contract 52,736.18 51,541.08
2. The value of work performed is less than the original contract
amount by $1,195.10 due to a general overestimation of planned
quantities.
3. It is hereby directed that final payment be made on said contract,
taking the Contractor's receipt in full. The total amount to be
paid for said improvement under said contract shall be $51,541.08.
September 24, 1984 OI eoeo
D to May
i
ATTEST:
Clerk
The motion for the adoption of the foregoing resolution was duly seconded by
member Celia Scott and upon vote being taken thereon, the following
voted in favor thereof: Dean Nyquist, Gene Lhotka, Celia Scott, Bill Hawes,
and Rich Theis;
and the following voted against the same: none,
whereupon said resolution was declared duly passed and adopted.