Loading...
HomeMy WebLinkAbout1983-131 CCRMember Gene Lhotka introduced the following resolution and moved its adoption: RESOLUTION NO. 83 -131 RESOLUTION ACCEPTING WORK PERFORMED UNDER CONTRACT 1983 -F (LIONS PARK TENNIS COURT IMPROVEMENT PROJECT NO. 1982 -20, PHASE II) WHEREAS, pursuant to written Contract 1983 -F signed with the City of Brooklyn Center, Minnesota, Tennis West, Ltd. has satisfactorily completed the following improvement in accordance with said contract: LIONS PARK TENNIS COURT IMPROVEMENT PROJECT NO. 1982 -20, PHASE II NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of Brooklyn Center, Minnesota, that: 1. The work completed under said contract and supplemental agreement is accepted and approved according to the following schedule: Previously Approved Final Amount Original Contract $21,224.00 $21,224.00 Supplemental Agreement 1,997.50 1,997.50 TOTAL $23,221.50 $23,221.50 C 2. The value of the work performed is equal to the sum of the original contract and supplemental agreement. 3. It is hereby directed that final payment be made on said contract, taking the Contractor's receipt in full. The total amount to be paid for said improvement under said contract shall be $23,221.50. September 12, 1983 Date A ATTEST: Clerk Mayor/, The motion for the adoption of the foregoing resolution was duly seconded by member Rich Theis and upon vote being taken thereon, the following voted in favor thereof:Dean Nyquist, Gene Lhotka, Bill Hawes, and Rich Theis; and the following voted against the same: none, whereupon said resolution was declared duly passed and adopted. �J