HomeMy WebLinkAbout1983-094 CCRMember Bill Hawes introduced the following resolution
and moved its adoption:
RESOLUTION NO. 83 -94
RESOLUTION ACCEPTING WORK PERFORMED UNDER CONTRACT 1982 -N
(LIFT STATION NO. 3 IMPROVEMENT PROJECT NO. 1982 -26)
WHEREAS, pursuant to written Contract 1982 -N signed with the City
of Brooklyn Center, Minnesota, Northdale Construction Company, Inc. has
satisfactorily completed the following improvement in accordance with said
contract:
LIFT STATION NO. 3 IMPROVEMENT PROJECT NO. 1982 -26
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of
Brooklyn Center, Minnesota, that:
1. The work completed under said contract and change order is
accepted and approved.
Original Award
Change Order #1
Change Order #2
1
TOTAL
Previously Approved
$46,500.00
(500.00)
252.94
$46,252.94
Final Amount
$46,500.00
(500.00)
252.94
$46,252.94
2. The value of work performed is equal to the sum of the original
contract and change orders amount.
3. It is hereby directed that final payment be made on said contract,
taking the Contractor's receipt in full. The total amount to be
paid for said improvement under said contract shall be $46 252.94.
July 11, 1983 o�
*D1 Mayor ATTEST:
The motion for the adoption of the foregoing resolution was duly seconded by
member Celia Scott and upon vote being taken thereof, the
following voted in favor thereof: Dean Nyquist, Gene Lhotka, Celia Scott,
Bill Hawes, and Rich Theis;
and the following voted against the same: none,
whereupon said resolution was declared duly passed and adopted.