HomeMy WebLinkAbout1978-166 CCR Member Tony Kuefler introduced the following resolution
and moved its adoption:
RESOLUTION NO. 78 -166
RESOLUTION ORDERING ADDITION OF AMENDED SANITARY SEWER
IMPROVEMENT PROJECT NO. 1978 -18 TO CONTRACT 1978 -D
WHEREAS, on June 19, 1978, the Brooklyn Center City Council
awarded Contract 1978 -D in the amount of $70,335.58 to Walhunt
Construction, Inc., on the basis of their bid being the lowest bid
received; and
WHEREAS, on August 14, 1978, the City Council adopted Resolution
No. 78- amending the description of Sanitary Sewer Improvement
Project No. 1978 -18; and
WHEREAS, Walhunt Construction, Inc., has agreed to perform the
additional work comprehended by the said amended Sanitary Sewer
Improvement Project No. 1978 -18 based upon the unit prices bid under
Contract 1978 -D and a price quotation for breaking into an existing
manhole deemed acceptable by the City Engineer; and
WHEREAS, the total cost of said additional work, as computed
on the basis of the aforementioned unit prices, increases the contract
amount for said project by approximately $2,700.00, representing an
increase of 3.8/ of the total contract amount of $70,335.58 for Contract
1978 -D.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City
of Brooklyn Center, that the City Engineer is hereby directed to add
the work comprehended under amended Sanitary Sewer Improvement Project
No. 1978 -18 to Contract 1978 -D with payment to be made in accordance
with the unit prices received, thereby increasing the contract amount
for said project by $2,700.00 to a total amount of $6,152.00.
August 14, 1978
Date r Ma��`�
ATTEST:
Clerk
The motion :for the adoption of the foregoing resolution was duly
seconded by member BillFignar and upon vote being taken
thereon, the following voted in favor of same: Dean Nyquist, Tony Kuefler,
Bill Fignar, Gene Lhotka, and Celia Scott;
and the following voted against the same: none,
whereupon said resolution was declared duly passed and adopted.