RESOLUTION NO 73 -180
RESOLUTION ESTABLISHING AND ORDERING CONSTRUCTION OF
STORM SEWER CORRECTIVE SITE IMPROVEMENT PROJECT
NO. 1973 -38, AND AUTHORIZING DISBURSEMENT OF MONIES
RECEIVED FROM SETTLEMENT OF THE BROOKDALE GARDENS LAWSUIT
WHEREAS, the City of Brooklyn Center approved site and
building plans for the Brookdale Gardens apartment complex owned
by Siegel Goldman on August 8, 1966; and
WHEREAS, the said owners executed a performance agreement
with the City of Brooklyn Center, agreeing to construct the said
site in accordance with plans approved by the City of Brooklyn
Center; and
WHEREAS, the said owners posted a bond in the amount of
$25,000.00 to guarantee performance of said agreement; and
WHEREAS, the storm water drainage system for said site was
not completed in accordance with said approved plans; and
WHEREAS, the City of Brooklyn Center initiated foreclosure
proceedings against the said bond to enforce the obligation of
said performance agreement; and
WHEREAS, the Hennepin County District Court ruled in favor
of the City of Brooklyn Center's said foreclosure proceedings; and
WHEREAS, the City of Brooklyn Center has received from the
said owners, in accordance with a stipulated settlement of the law-
suit, the sum of $25,000.00, which has been deposited in an escrow
account in the City's Investment Trust Fund; and
WHEREAS, the said Court stipulated that of the $25,000.00
awarded to the City of Brooklyn Center to establish a storm water
run -off and storm sewer system upon said site, substantially in
accordance with the testimony of William E. Jensen, P. E., of
Suburban Engineering, Inc., $5,132.96 be deducted to reimburse
the City for attorney's fees, consulting engineering fees, expert
witness fees, and Court depositions; and
WHEREAS, the City Treasurer for the City of Brooklyn
Center has made the following payments from the General Fund:
RESOLUTION NO. 73 -180
1. Attorney's fees: $2,664.96
2. Verification of site data, analysis of
storm drainage problem, and preparation
of feasibility study by William E. Jensen: 2,000.00
3. Expert witness fees for trial testimony: 440.00
4. Depositions: 28.00
Total Amount: $5,132.96
and
WHEREAS, the said Court further stipulated that the said
corrective storm sewer work be completed and supervised by
Suburban Engineering, Inc., and be designed to be completed at
a cost not to exceed $19,867.04; and
WHEREAS, the said Court further stipulated that the said
owners agree to cooperate fully with the City on all requests
made in furtherance of the work, including the granting of con-
struction easements where required; and
WHEREAS, the establishing of an optimum storm water run-
off and storm sewer system upon said site in accordance with the
testimony of William E. Jensen, P. E., of Suburban Engineering,
Inc., is estimated to cost $25,650.00; and
WHEREAS, it is recognized by the City Council of the City
of Brooklyn Center that a modification of design is necessary to
construct the corrective storm sewer system for said site with
the above financial limitations; and
WHEREAS, in order to carry out the stipulation of said
Court, the City Council deems it necessary to initiate and order
construction of Storm Sewer Corrective Site Improvement Project
No. 1973 -38;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the
City of Brooklyn Center, Minnesota, that it is hereby determined
that it is necessary and for the best interests of the City that
Storm Sewer Corrective Site Improvement Project No. 1973 -38
shall be constructed, described as follows:
RESOLUTION NO. 73 -180
1973 -38 Storm Sewer Corrective Site Improvement
Corrective storm sewer, site grading, parking lot work,
and related engineering fees for the Brookdale Gardens
bond foreclosure, as directed by Court action (southerly
of 53rd Avenue North between T.H. 152 and Drew Avenue
North).
The estimated cost of $19,867.04 is to be financed by the
monies received in accordance with the Court stipulation.
BE IT FURTHER RESOLVED that the City Treasurer is hereby
authorized as follows:
1. To transfer $5,132.96 from the said Investment Trust
Fund Escrow Account to the General Fund for reimburse-
ment of previously paid expenses relative to the
Brookdale Gardens bond foreclosure.
2. To disburse funds from the said Investment Trust Fund
Escrow Account to pay the costs of Storm Sewer
Corrective Site Improvement Project No. 1973 -38 as
they occur, not to exceed $19,867.04.
NovPmh 5,
Date Mayo Pro T�
ATTEST:
Clerk
The motion for the adoption of the foregoing resolution was duly
seconded by member Tony Kuefler and upon vote being taken
thereon, the following voted in favor thereof: john Leary, Maurice
Britts Bill Fignar and Tony Kuefler;
and the following voted against the same: none,
whereupon said resolution was declared duly passed and adopted.