HomeMy WebLinkAbout1965-019 CCR Member Tohn Leary introduced the following resolution and
moved its adoption:
RESOLUTION NO. 65 -19
RESOLUTION AUTHORIZING A DELAY IN THE START OF CONSTRUCTION
ON THE BROOKLYN CENTER LIBRARY
WHEREAS, the contractor awarded the contract for general construction
of the Brooklyn Center Public Library has requested a deferral of the starting
date of construction from March 1, 1965 to April 1, 1965 due to inclement
weather and the depth of frost penetration; and
WHEREAS, the architect retained to design the library and oversee its
construction feels that such a deferral will not affect the anticipated completion
date of mid September; and
WHEREAS, the architect and other contractors associated with the
construction of the Library are in agreement with the proposed deferral:
NOW, THEREFORE, BE IT RESOLVED by the Village Council of the Village
of Brooklyn Center as follows:
1. The contractor for the general construction of the Library, Dean L.
Witcher, is authorized to defer the start of construction on said Library until
April 1, 1965, provided the construction time of 200 days specified in the
contract for general construction is computed from March 1, 1965.
2. A copy of this resolution shall be certified to the firm of Cerny
Associates and Dean L. Witcher.
February 23, 1965
Date Mayor
ATTEST: &J Ct
Clerk
The motion for the adoption of the foregoing resolution was duly seconded
by member Howard Heck and upon vote being taken thereon the following
voted in favor thereof: Gordon Erickson, Howard Heck, john Leary and
Earl Simons
and the following voted against the same: None
whereupon said resolution was declared duly passed and adopted.