HomeMy WebLinkAbout1991-026 EDAR1
1
Commissioner Celia Scott
resolution and moved its adoption:
EDA RESOLUTION NO. 91 -26
introduced the following
RESOLUTION AUTHORIZING PHASE II CONSTRUCTION FOR
SOUNDPROOFING HIPPODROME CHILLER
WHEREAS, the Economic Development Authority in and for
the City of Brooklyn Center (EDA) has completed Phase I of the
soundproofing of the Earle Brown Heritage Center chiller; and
WHEREAS, Phase I of the soundproofing did not provide
adequate sound reduction; and
WHEREAS, the current sound level from the chiller exceeds
state mandated noise levels; and
WHEREAS, the EDA coordinator has obtained quotations for
the completion of Phase II in the amount of $13,187.
NOW, THEREFORE, BE IT RESOLVED by the Economic
Development Authority in and for the City of Brooklyn Center that
Phase II of the Heritage Center chiller noise reduction plan is
approved and the EDA coordinator is authorized to complete the
project as part of the carryover costs of the original restoration.
A u zust 26. 1991
Date President
The motion for the adoption of the foregoing resolution was duly
seconded by Commissioner Philip Cohen and upon vote being
taken thereon, the following voted in favor thereof:
Todd Paulson, Celia Scott, Jerry Pedlar, Dave Rosene, and Philip Cohen;
and the following voted against the same: none,
whereupon said resolution was declared duly passed and adopted.