City of Brooklyn Center
March 10, 2008 AGENDA
1. Call to Order
—The EDA requests that attendees turn off cell phones and pagers during the meeting. A
copy of the full City Council packet, including EDA (Economic Development Authority), is
available to the public. The packet ring binder is located at the front of the Council
Chambers by the Secretary.
2. Roll Call
3. Approval of Agenda and Consent Agenda
—The following items are considered to be routine by the Economic Development Authority
(EDA) and will be enacted by one motion. There will be no separate discussion of these
items unless a Commissioner so requests, in which event the item will be removed from the
consent agenda and considered at the end of Commission Consideration Items.
a. Approval of Minutes
L February 25, 2008 Regular Session
4. Commission Consideration Items
a. Resolution Opting Not to Waive Limited Tort Liability for 2008
-Requested Commission Action:
Motion to adopt resolution.
b. Resolution Approving Change Order No. 1, Accepting Work Performed and
Authorizing Final Payment, Improvement Project No. 2007 -15, TIF District 3
Regional Storm Water Treatment Improvements
-Requested Council Action:
Motion to adopt resolution.
5. Adjournment
i
FI►A Ngeft
da -item No. 3a
MINUTES OF THE PROCEEDINGS OF THE
ECONOMIC DEVELOPMENT AUTHORITY
OF THE CITY OF BROOKLYN CENTER
IN THE COUNTY OF HENNEPIN AND THE
STATE OF MINNESOTA
REGULAR SESSION
FEBRUARY 25, 2008
CITY HALL COUNCIL CHAMBERS
1. CALL TO ORDER
The Brooklyn Center Economic Development Authority (EDA) met in Regular Session called to
order by President Tim Willson at 8:18 p.m.
2. ROLL CALL
President Tim Willson and Commissioners Kay Lasman, Mary O'Connor, Dan Ryan, and Mark
Yelich. Also present were Executive Director /City Manager Curt Boganey, Engineering
Technician IV Bruce Johnson, Community Development Director Gary Eitel, Planning and
Zoning Specialist Ron Warren, City Attorney Charlie LeFevere, and Carol Hamer, TimeSaver
Secretarial, Inc.
3. APPROVAL OF AGENDA AND CONSENT AGENDA
Commissioner Lasman moved and Commissioner Ryan seconded approval of the Agenda and
Consent Agenda, and the following item was approved:
3a. APPROVAL OF MINUTES
1. January 14, 2008 Regular Session
Motion passed unanimously.
4. COMMISSION CONSIDERATION ITEMS
4a. RESOLUTION NO. 2008 -02 AUTHORIZING EXECUTION OF A
DEVELOPMENT AGREEMENT AND REAL ESTATE OPTION AGREEMENT
(NORTHERN 8+ ACRES OF THE I -694 HWY 100 REDEVELOPMENT SITE)
Mr. Boganey introduced the item, discussed the history, and stated the purpose of the proposed
resolution. He provided an overview of the Option and Development Agreement with U.S.
General Services Administration (GSA).
It was noted that environmental issues related to a fuel tank leak on the property are not expected
to significantly alter the timeframe associated with the redevelopment
Mr. Forrest Hudson, representing GSA, addressed the EDA and answered questions of the
Commissioners.
02/25/08 -1- DRAFT
There was discussion of the following issues in relation to the development agreement and real
estate option agreement:
Perimeter security fence planned on the site
EDA economic participation in the project
Redevelopment efforts in the City
Value of the site
Anticipated tax capacity with the proposed project
Possible effects of the project in moving up the decertification date of the tax increment
financing district
Commissioner Lasman moved and Commissioner Ryan seconded adoption of EDA
RESOLUTION NO. 2008 -02 Authorizing Execution of a Development Agreement and Real
Estate Option agreement (Northern 8+ acres of the I -694 Hwy 100 Redevelopment Site).
Commissioner Yelich stated although this is an intriguing project and is in line with the direction
outlined by the City Council, he will be voting against the resolution due to the business subsidy
going to the federal government.
Commissioners O'Connor and Yelich voted against the same. Motion passed.
President Willson stated this project is an excellent first step in spurring redevelopment in the
City. He welcomed the GSA and FBI to the City of Brooklyn Center.
5. ADJOURNMENT
Commissioner Lasman moved and Commissioner Ryan seconded adjournment of the Economic
Development Authority meeting at 8:52 p.m.
Motion passed unanimously.
02/25/08 -2- DRAFT
EDA Agenda Item No. 4a
X City of Brooklyn Center
Economic Development Authority Agenda Item Memorandum
TO: Curt Boganey, Executive Director
FROM: Daniel Jordet, Assistant Treasurer
DATE: 29 February 2008
SUBJECT: Statutory Tort Liability Limits
Recommendation:
It is recommended that the attached resolution adopting the, no waiver option for
statutory tort liability insurance be adopted by the EDA.
Background:
Each year the EDA must chose whether to waive tort liability limit protections of
Minnesota Statutes 466.04 as part of the insurance policy renewal application
process. M.S. 466.04 states that the maximum liability for an insured for any
claim arising after 1 January 2008 but before 1 July 2009 is 400,000 with an
aggregate maximum of 1,200,000 per incident. This limitation automatically
rose from the 300,000/$ 1,000,000 limitation last year under legislation
adopted in 2006 and will rise again after 1 July 2009 to 500,000/$ 1,500,000.
Our regular liability insurance policy covers claims under the strictures of this
statute.
If the EDA were to waive the limits set by statute, it would be prudent to
purchase additional insurance coverage to cover possible higher awards in
liability claims. Premiums for such insurance would exceed 7,000 per year.
Financial Impact:
The 2008 budget anticipates leaving the no waiver option in place for 2008 and
has anticipated insurance premiums based on that n waiver option. Waiving the
statutory limits would require that at least 7,000 in additional premium costs
be allocated for 2008 and in each succeeding year.
LEAGUE OF MINNESOTA CITIES INSURANCE TRUST
LIABILITY COVERAGE -WAIVER FORM
Cities obtaining liability coverage from the League of Minnesota Cities Insurance Trust must decide
whether or not to waive the statutory tort liability limits to the extent of the coverage purchased. The
decision to waive or not to waive the statutory limits has the following effects:
If the city does not waive the statutory tort limits, an individual claimant would be able to recover no
more than $400,000.on any claim to which the statutory tort limits apply. The total which all claimants
would be able to recover for a single occurrence to which the statutory tort limits apply would be
limited to $1,200,000. These statutory tort limits would apply regardless of whether or not the city
purchases the optional excess liability coverage.
0 If the city waives the statutory tort limits and does not purchase excess liability coverage, a single
claimant could potentially recover up to $1,200,000. on a single occurrence. The total which all
claimants would be able to recover for a single occurrence to which the statutory tort limits apply would
also be limited to $1,200,000., regardless of the number of claimants.
If the city waives the statutory tort limits and purchases excess liability coverage, a single claimant
could potentially recover an amount up to the limit of the coverage purchased. The total which all
claimants would be able to recover for a single occurrence to which the statutory tort limits apply would
also be limited to the amount of coverage purchased, regardless of the number of claimants.
Claims to which the statutory municipal tort limits do not apply are not affected by this decision.
This decision must be made by the city council. Cities purchasing coverage must complete and
return this form to LMCIT before the effective date of the coverage. For further information, contact
LMCIT. You may also wish to discuss these issues with your city attorney.
Brooklvn Center EDA and HRA accepts liability coverage limits of from the
League of Minnesota Cities Insurance Trust (LMCIT).
Che one:
The city DOES NOT WAIVE the monetary limits on municipal tort liability established by
Minnesota Statutes 466.04.
The city WAIVES the monetary limits on tort liability established by Minnesota Statutes 466.04,
to the extent of the limits of the liability coverage obtained from LMCIT.
Date of city council meeting
Signature /Date Position
Return this completed form to LMCIT, 145 University Ave. W,, 5t. Paul, MN. 551032044
LMCIT (11 /00)(Rev.11 /07) Page 1 of 1
466.04, Minnesota Statute Page 1 of 1
2007 Minnesota Statutes
4 MAXIMUM LIABILITY.
Wivision 1. Limits; punitive damages. (a) Liability of any municipality on any claim
within the scope of sections 466.01 to 466.15 shall not exceed:
(1) $300,000 when the claim is one for death by wrongful act or omission and $300,000 to
any claimant in any other case, for claims arising before January 1, 2008;
(2) $400,000 when the claim is one for death by wrongful act or omission and $400,000
to any claimant in any other case, for claims arising on or after January 1, 2008, and before
July 1, 2009;
(3) $500,000 when the claim is one for death by wrongful act or omission and $500,000 to
any claimant in any other case, for claims arising on or after July 1, 2009;
(4) $750,000 for any number of claims arising out of a single occurrence, for claims arising
on or after January 1, 1998, and before January 1, 2000;
(5) $1,000,000 for any number of claims arising out of a single occurrence, for claims arising
on or after January 1, 2000, and before January 1, 2008;
(6) $1,200,000 for any number of claims arising out of a single occurrence, for claims arising
on or after January 1, 2008, and before July 1, 2009;
(7) $1,500,000 for any number of claims arising out of a single occurrence, for claims
arising on or after July 1, 2009; or
(8) twice the limits provided in clauses (1) to (7) when the claim arises out of the release
or threatened release of a hazardous substance, whether the claim is brought under sections
11513.01 to 115B.15 or under any other law.
(b) No award for damages on any such claim shall include punitive damages.
Subd. 1 a. Officers and employees. The liability of an officer or an employee of any
municipality for a tort arising out of an alleged act or omission occurring in the performance of
duty shall not exceed the limits set forth in subdivision 1, unless the officer or employee provides
pr sional services and also is employed in the profession for compensation by a person or.
other than the municipality.
d. 1 b. Total claim. The total liability of the municipality on a claim against it and against
its officers or employees arising out of a single occurrence shall not exceed the limits set forth in
subdivision 1.
Subd. 2. Inclusions. The limitation imposed by this section on individual claimants includes
damages claimed for loss of services or loss of support arising out of the same tort.
Subd. 3. Disposition of multiple claims. Where the amount awarded to or settled upon
multiple claimants exceeds the applicable limit under subdivision 1, paragraph (a), clauses (2)
to (4), any party may apply to any district court to apportion to each claimant a proper share of
the total amount limited by subdivision 1. The share apportioned each claimant shall be in the
proportion that the ratio of the award or settlement made to each bears to the aggregate awards
and settlements for all claims arising out of the occurrence.
History: 1963 c 798 s 4; 1976 c 264 s 1 -3; 1983 c 121 s 28; 1983 c 331 s 2,3; 1986 c 444;
1989 c 325 s 50; 1997 c 210 s 3,4; 2006 c 232 s 2
NOTE: The amendment to subdivision 1 by Laws 2006, chapter 232, section 2, is effective
January 1, 2008. Laws 2006, chapter 232, section 2, the effective date.
https:/ /www.revisor.leg.state.mn.us /statutes ?id= 466.04 2/29/2008
Commissioner introduced the following resolution and moved
its adoption:
EDA RESOLUTION NO.
RESOLUTION OPTING NOT TO WAIVE LIMITED TORT LIABILITY FOR
2008
WHEREAS, the Economic Development Authority of the City of Brooklyn Center
has an option to waive its protection under the tort liability limitation contained in Minnesota
Statutes 466.04; and
WHEREAS, the statutory tort limit for 2008 is $400,000 per individual with an
aggregate of $1,200,000 per incident; and
WHEREAS, the Economic Development Authority of the City of Brooklyn Center
has not opted to waive its rights to limited tort liability in past years and is required to make a
declaration of its intention every year.
NOW, THEREFORE, BE IT RESOLVED by the Economic Development Authority
of the City of Brooklyn Center that the Authority does not waive the monetary limits on municipal
tort liability established by Minnesota Statutes 466.04 for 2008.
March 10, 2008
Date President
The motion for the adoption of the foregoing resolution was duly seconded by commissioner
and upon vote being taken thereon, the following voted in favor thereof:
and the following voted against the same:
whereupon said resolution was declared duly passed and adopted.
DA Agenda Item N 4b
E
1
COUNCIL ITEM MEMORANDUM
TO: Curt Boganey, City Manager
FROM: Todd Blomstrom, Director of Public Works
DATE: March 4, 2008
SUBJECT: Resolution Approving Change Order No. 1, Accepting Work Performed and
Authorizing Final Payment, Improvement Project No. 2007 -15, TIF District 3
Regional Storm Water Treatment Improvements
Recommendation:
Public Works staff recommends that the Brooklyn Center City Council consider the attached
resolution approving Change Order No. 1, accepting work performed and authorizing final
payment for Improvement Project No. 2007 -15, TIF District 3 Regional Storm Water Quality
Treatment Improvements.
Background:
On August 13, 2007 the Economic Development Authority awarded a contract for
Improvement Project 2007 -15 to Thomas Sons Construction Company, Inc. of Rogers,
Minnesota for the construction of the storm water treatment improvements near the
intersection of State Highway 252 and 66 Avenue North. Thomas Sons Construction has
completed the construction work and is now requesting final payment for the project.
During the course of construction, the Contractor submitted claims for extra work. A majority of
the claims for extra work are associated with the discovery of underground utilities that were not
clearly depicted on the project bid documents prepared by WSB Associates, the engineering
consultant for the project.
The engineering consulting has reviewed the claims and provided a formal recommendation to
the City. The following documents related to the extra work claims are attached to this
memorandum.
Document 1 Letter from WSB Associates, dated January 8, 2008, itemizing the
recommended payment for extra claims;
Document 2 A second letter from WSB Associates, dated January 8, 2008 describing
their proposed contribution towards the extra costs associated with underground utilities
that were not depicted on the project bid documents;
Document 3 Proposed Change Order No: 1 form.
is The contractor has submitted claims for. extra work totaling $48,658.29. The engineering
consultant has recommended that $42,623.89 of the extra work claims are justified and should be
Improvement Project 2007 -15 Change Order No. I
paid to the contractor. The attached Change Order No. I was prepared based on the engineer's
recommendations and presented to the contractor for consideration. The contractor has accepted
and executed the proposed change order and accepts the proposed final contract payment amount
recommended by the consulting engineer.
Budget Issues:
The attached resolution approves Change Order No. l for the project. The original contract
amount is $1,040,842.50_ The change order would increase the contact amount by
$42,623.89. The project engineering consultant has offered to reimburse the City in the
amount of $15,270.00 ($12,500 contract cost and $2,770 services credit) for a portion of the
cost associated with the Change Order.
Improvement Project 2007 -15 Change Order No. 1
WSB
Associates, Inc. Infrastructure 1 Engineering 1 Planning 1 Construction 701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Janua 8 2008 Tel: 763-541-4800
Fax: 763-541-1700
Mr. Todd Blomstrom
City Brooklyn of Brookl Center D OCUMENT 1
01 Shingle Creek Parkway
G3 S g k rar y
Brooklyn Center, MN 55430
Re: Thomas and Sons' Requests for Additional Payment
TIF District 3 Regional Stormwater Treatment Project
WSB Project No. 1143 -05
Dear Mr. Blomstrom:
This letter addresses Thomas and Sons' requests for additional payment pertaining to the TIF
District 3 Regional Stormwater Treatment Project.
A summary of Thomas and Sons' requests are provided on the attached sheet. It is recommended
that payment in the amount of $42,623.89 be provided to Thomas and Sons to address their requests
for additional payment. This amount includes $32,750.00 that should be provided to Thomas and
Sons for work associated with Request Nos. 2, 3, 5, and 6, and approximately 90% of 11 pertaining
to utilities that were not indicated on bid documents. In addition payment ent of $1,250 should be
p
provided for silt curtain as noted in Request No. 12, and $8,623.89 should be provided for repairing
a leaking sanitary sewer service and resetting footing forms that were impacted by the leak as noted
under request No. 14. These requests are items that the contractor could not anticipate based on the
bid documents. Therefore, it is reasonable and necessary to pay the contractor for this work.
Payment should be denied for other requests based on the following:
Request Nos. 1, 4, 10 and 13
Per email correspondence dated October 26, 2007, payment for Request Nos. 1, 4, and 10
has been previously denied as indicated on the attached email. Similarly, Request No. 13 is
considered an incidental cost to the project, and, as stated in phone conversation with Dan
Thomas on November 6 prior to work being performed, no additional payment will be
made for Request No. 13.
Request No. 7
Request No. 7 was nullified, with a credit under Request No. 8.
Minneapolis 1 St. Cloud
Equal Opportunity Employer K: iOL/ 4!- OSUldminiDocs�LTR- tblomstrom1- revised 0/0808.doc
Mr. Todd Blomstrom
January 8, 2008
Page 2
Request No. 9
Work associated with Request No. 9 was also included in the invoice under Request No. 11.
This was confirmed by Steve Thomas Jr., of Thomas and Sons, and it was agreed that a
credit of $1,446 should be applied to offset the fees associated with No. 9 since it was re-
issued on No. 11.
Request No. 11
$29,350 of the requested $31,947.29 should be paid for Request No. 11. The contractor
claimed that the Komatsu 800 was necessary to work around existing utilities that were not
shown on the bid plans. Therefore, it was agreed that the contractor would be paid for the
upgraded rental price of the larger excavator for the time necessary to work around the
utilities that were not indicated on the plans. In specific, the City authorized payment to the
contractor for each day that the excavator would be used to construct structures A and B and
new arch pipe installed near the utilities that were not located in bid plans.
If you have any questions regarding this recommendation, please contact me.
Sincerely,
WSB Associates, Inc.
Todd E. Hubmer, PE
Principal/Project Manager
Attachment
cc: Bruce Johnson, City of Brooklyn Center
Paul Hudalla, WSB Associates, Inc.
ti;!143- uj,idminLDocsLLrR- thionistrom2 120307.doc
i
City of Brooklyn Center
TIF District 3 Regional Stormwater Treatment System
WSB No. 1143 -05
Thomas and Sons' Requests for Additional Payment
Item Invoice Invoice Date Net Amount Description
112770 -01 9/18/20071 $1,500.00 lRemove and Replace Light Poles
22770 -02 N 9/18/20071 $1,056.00 lWork Around Existinq Utilities for Potholinq
312770 -02 1 10/11/20071 $908.00 ISupport Cables on Sheetinq (4 sections sheetinq)
412770 -03 1 9/18/20071 $2,112.00 (Remove and Replace 36" RCP and MH
512770 -03 10/11/20071 $528.00 lWork Around Existing Utilities
612770 -04 1 10/18/20071 $908.00 Work Around Existinq Utilities
712770 -05 1 10/19/20071 $1,446.00 ISetup and Tear Down Komatsu 800
812770 -05 1 10/19/20071 ($1,446.00)lSetup and Tear Down Komatsu 800
92770 -05A 1 10/15/20071 $1,446.00 )Setup and Tear Down Komatsu 800
1012770 -06 11/5/20071 $5,970.61 lRemove 18" Pipe and Construct 36" RCP, FES, CBMH
1112770-07 11/6/20071 $31,947.29 +Komatsu 800 from 9/10 to 10/11
1212770 -08 1 11/15/20071 $1,250.00 IFioatinq Silt Curtain
1312770 -09 1 11/16/20071 $1,032.39 11-andscape in Islands
A
WSB
VA,sociates, Inc. Infrastructure 1 Engineering 1 Planning 1 Construction 701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
January 8, 2008 Tel:763- 541 -4800
Fax: 763 -541 -1700
City Todd Brooklyn Ce nter DOCUMENT #2
City of Brooklyn Center
6301 Shingle Creek Parkway
Brooklyn Center, MN 55430
Re: TIF District 3 Regional Stormwater Treatment System
WSB Project No. 1143 -05
Dear Mr. Blomstrom:
WSB &Associates, Inc. (WSB) is presenting a proposal for your consideration to resolve extra
costs incurred by the City of Brooklyn Center due to utility issues on the TIF District 3 Regional
Stormwater Treatment System Project.
As you are aware, the locations of utilities were not clearly defined on the plans prepared for the bid
package dated July 25, 2007. The bid was awarded for construction, and upon the construction
locate called by the selected contractor, we were notified utilities had been marked that were not
located prior to awarding the project.
The following observations have factored into our proposed action to resolve this issue:
1. Some existing private utilities located within the project limits were not shown on
bid plans.
2. The design of the TIF District 3 project did not conflict with the private utilities
located on the site. Therefore, the design of the treatment system and specifications
did not need modification to accommodate the location of private utilities.
3. If the private utility information was shown on the bid documents, it is reasonable to
assume the City would have seen an increase in bid pricing to reflect the time and
materials necessary to work adjacent to and around the private utilities.
4. The utility companies would not have relocated their utilities even if the issues were
known ahead of time. The chosen contractor would have needed to work around the
utilities and those costs would have been included in the City project costs.
5. Under typical circumstances, WSB would have recommended to the City of
Brooklyn Center to rebid the project. WSB would have revised, published,
advertized, and distributed bid documents to bidders at no cost to the City. However,
due to the funding timetables and expiration dates for temporary easements, this was
not a reasonable option to pursue. Therefore, prior to beginning construction, WSB
Minneapolis 1 St. Cloud
Equal Opportunity Employer K: 101143- 05UdminlDoesILTR- tblomstrom- revised- 010808.doc
Mr. Todd Blomstrom
January 8, 2008
Page 2
worked closely with City staff to identify the potential liabilities for the project.
WSB committed to the City of Brooklyn Center to contribute to the additional costs
associated with working around the utilities in lieu of incurring the costs to revise the
plans, bid documents, and rebid the project.
WSB Associates, Inc. has reviewed the additional payment requested by the contractor associated
with the utility conflicts on the project and has recommended the City of Brooklyn Center
compensate the contractor approximately $32,750 to address the private utility issues.
In conformance with our commitment to the City of Brooklyn Center, WSB proposes the following
to resolve the issues with the private utilities not being shown on the construction plans:
1. WSB deducted $2,770 on our November 20, 2007, invoice for services associated
with staff time to resolve the conflict issues and to work with the contractor.
2. WSB proposes to contribute an additional $12,500 toward the resolution of this
issue.
Therefore, WSB Associates, Inc. is proposing to contribute $15,270 toward the resolution of this
issue. This amount is greater than the estimated cost of $8,000 to $10,000 WSB would have
incurred in revising the bid documents and conducting a new bid process for the project. Though
we regret these situations arise, we feel the proposal presented to resolve this issue is fair and
reasonable and represents our commitment to you.
We appreciate the opportunity to work with the City of Brooklyn Center, and we hope that you find
the terms outlined in this letter acceptable. If you have any questions, please feel free to call me at
763- 287 -7182.
Sincerely,
WSB Associates, Inc.
7 �",A• p'''er
Todd E. Hubmer, PE
Principal/Project Manager
cc: Bret Weiss, WSB Associates, Inc.
Pete Willenbring, WSB Associates, Inc.
Paul Hudalla, WSB Associates, Inc.
K:1 143 -05 tAdmin lDocs ILTR- rbloms from- I 20307.doc
City of Brooklyn Center
I I
CHANGE ORDER NO. 2
Contractor: Thomas and Sons Construction January 8, 2007
Address: 13925 Northdale Boulevard
P.O. Box 303
Rogers, MN 55374 -9461
Project: TIF District 3 Regional Stormwater
Treatment System
Improvement Project No. 2007 -15
Contract No. 2007 -G
The following items were not included within the terms of Contract 2007 -G, but deemed necessary to
complete the project in accordance with the intended design. As of January 8, 2007 the project is
substantially complete. This change order resolves all requests for payment of extra work associated with
the contract. The Contractor has no additional requests for extra work beyond those items itemized herein.
The Contractor has satisfied payments to all subcontractors and material suppliers in -full and will provide
lien waivers from all subcontractors and material suppliers for work associated with Contract 2007 -G.
1. EXPLORATORY EXCAVATION
This item provides full compensation for all labor, materials, equipment and miscellaneous costs
associated with exploratory excavation at locations of underground utilities that were not shown on
the bid documents.
Thomas Sons Invoice No. 2770 -02: $1,056.00
2. SUPPORT CABLES ON SHEETING
This item provides full compensation for all labor, materials, equipment and miscellaneous costs
associated with furnishing, installing, maintaining and removal of sheeting to provide temporary
I
support of underground utilities that were not shown on the bid documents.
Thomas Sons Invoice No. 2770 -02: $908.00
3. WORK AROUND EXISTING UTILITIES
This item provides full compensation for all labor, materials and miscellaneous costs associated
with additional work around existing underground utilities that were not shown on the bid
documents. Extra equipment costs are provided in Item 4 below.
Thomas Sons Invoice No. 2770 -03: $528.00
Thomas Sons Invoice No. 2770 -04: $908.00
4. KOMATSU 800 EXCAVATOR
This item provides full compensation for all labor, materials, equipment and miscellaneous costs
associated with the upgraded rental price of a larger excavator machine to work around the
underground utilities that were not shown on the bid documents. Total additional compensation
for the larger excavator is ninety -one (91) percent of the amount shown on Invoice No. 2770 -07.
The remaining nine (9) percent of Invoice No. 2770 -07 is denied. This item includes the
proportional share of compensation for delivery, setup, tear down and removal of the equipment
from the site.
Thomas Sons Invoice No. 2770 -07: $29,350.00
Page 1 of 2
Change Order No.1
Contract 2007 -G
December 21, 2007
5. EROSION CONTROL SILT CURTAIN
This item provides full compensation for all labor, materials, equipment and miscellaneous costs to
furnish, install, maintain and remove the temporary floating silt curtain within the existing storm
water pond adjacent to the construction zone.
Thomas Sons Invoice No. 2770 -08: $1,250.0
6. SANITARY SEWER REPAIR
This item provides full compensation for all labor, materials, equipment and miscellaneous costs
associated with sanitary sewer services that were encountered within the project.
Total Cost: 8,623.89
7. CANCELED INVOICES
The Contractor hereby cancels Invoice Nos. 2770 -01, 2770 -03 (portion dated 9/18/07), 2770 -05,
2770 -05A, 2770 -06 and 2770 -09. The Contractor no longer seeks compensation for these items.
CONTRACT ADJUSTMENT
Original Contract Amount 1,040,842.50
Change Order No. 1 42.623.89
Revised Contract Amount 1,083,466.39
CHANGE IN CONTRACT TIlVI E
The Contract completion date is not changed due to the items noted above.
Accepted: TBOMAS SONS Approved: CITY OF BROOKLYN CENTER
CONSTRUCTION, INC.
By,koll& -ems By:
ContraEWs Authorized Re resentative City Manager
Dates -47 q d Date:
By:
Director of Public Works
Date:
Page 2 of 2
Member introduced the following resolution and moved its
adoption:
RESOLUTION NO.
RESOLUTION APPROVING CHANGE ORDER NO. 1, ACCEPTING WORK
PERFORMED AND AUTHORIZING FINAL PAYMENT, IMPROVEMENT
PROJECT NO. 2007 -15, TIF DISTRICT 3 REGIONAL STORM WATER
QUALITY TREATMENT IMPROVEMENTS
WHEREAS, pursuant to a written contract signed with the City of Brooklyn Center,
Minnesota, Thomas Sons Construction Company, Inc. of Rogers, Minnesota has completed the
following improvement in accordance with said contract: Improvement Project No. 2007 -15, TIF
District 3 Regional Storm Water Quality Treatment Improvements; and
WHEREAS, during the initial phases of construction, underground utility lines were
discovered within the construction limits of Improvement Project No. 2007-15 that were not shown
on the bid documents prepared by the project consultant; and
WHEREAS, installation of underground piping for the project required additional labor,
equipment and materials as a result of said underground utility lines; and
WHEREAS, the Contractor and City have mutually agreed that $42,623.89 in extra work
was necessary to complete the project based on the intended design; and
WHEREAS, the engineering consultant for the project has offered to contribute $12,500
toward the cost of the extra work and $2,770 toward the cost of additional engineering services.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Brooklyn
Center, Minnesota that:
1. Change Order No. 1 in the amount of $42,623.89 is hereby approved.
2. Final
r 'ect No. 2007 -15 TIF
shall be made on Improvement o
payment P P J
ri Regional Storm Water Treatment Improvements taken
District 3 Reg p g the
contractor's receipt in full. The total estimated amount to be paid for said
improvements under said contract shall be 1,083,466.39.
3. The amended project costs for Improvement Project No. 2007 -15 is provided
below. The revenue for the project costs shall be derived from tax increment
revenues generated by Tax Increment Financing District No. 3.
RESOLUTION NO.
COSTS
Construction Contract $1,083,466.39
Eng, Legal, Administration 45,714.07
Land Acquisition 18,735.59
Testing and Inspection 5,773.03
Sewer Line Repair 423.38
Permits and Approvals 1.000.00
Total Est. Project Costs $1,155,112.46
March 10, 2008
Date Mayor
ATTEST:
City Clerk
The motion for the adoption of the foregoing resolution was duly seconded by member
p g g Y
and upon vote being taken thereon, the following voted in favor thereof:
and the followin g g voted against the same:
whereupon said resolution was declared duly passed and adopted.