Member Kathleen Carmody introduced the following resolution and moved
its adoption:
RESOLUTION NO. 2006-137
RESOLUTION APPROVING CHANGE ORDER NO. 1, IMPROVEMENT
PROJECT NO. 2006-11, CONTRACT 2006-E, CENTRAL/SALT STORAGE
FACILITY IMPROVEMENTS
WHEREAS, pursuant to a written contract signed with the City of Brooklyn
Center, Minnesota, Greystone Construction Company of Shakopee, Minnesota was instructed to
modify the material specifications for exterior finishes on the pre-cast concrete building panels as
itemized on Change Order No. 1 for Contract 2006-E; and
WHEREAS, said additional work was not included in the original Contract, but
was deemed cost effective and justified for the project.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brooklyn Center, Minnesota that Change Order No. 1 in the amount of $3,626.00 is hereby
approved. The revised contract amount shall be as follows:
Original Contract Amount
Change Order No. 1
Revised Contract Amount
$ 337,716.00
$ 3.626.00
$ 341,342.00
ATTEST: VA&L Tl .
City Clerk
November 27, 2006
Date
D
Mayor
The motion for the adoption of the foregoing resolution was duly seconded by member
Kay Lasman
and upon vote being taken thereon, the following voted in favor thereof:
Myrna Kragness, Kathleen Carmody, Kay Lasman, and Diane Niesen;
and the following voted against the same: Mary O'Connor;
whereupon said resolution was declared duly passed and adopted.