RESOLUTION NO. 2009 -135
RESOLUTION ACCEPTING PROJECT NO. 2008 -16, CONTRACT 2008 -J,
AUTOMATIC METER READING PROJECT AND AUTHORIZING FINAL
PAYMENT TO NORTHERN WATER WORKS, INC.
WHEREAS, pursuant to a written Contract signed with the City of Brooklyn Center,
Northern Water Works Supply of Blaine Minnesota has completed the following improvement in
accordance with said Contract:
Improvement Project No. 2008 -16, Contract 2008 -J, Automatic Meter Reading.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brooklyn Center, Minnesota that:
1. Final payment shall be made on Improvement Project No. 2008 -16, Contract
2008 -J, Automatic Meter Reading, taking the Contractor's receipt in full.
The total amount to be paid to the Contractor for said improvements under
said Contract shall be $2,135,621.17
2. The estimated project costs and revenues are hereby amended as follows:
Original Award
COSTS Amount Final Amount
Contract 2,322,573.25 2,110,958.09
Changer Order 1 21,036.80
Changer Order 2 3,626.28
Subtotal Contract Costs 2,322,573.25 2,135,621.17
Contingency Costs 100,000.00 68,756.77
Admin/Eneineerine /Lecial 84,800.00 91,870.24
Total Project Cost 2,507,373.25 2,296,248.18
Original Award
REVENUE Amount Final Amount
Water Utility Fund 1,880,529.94 1,722,186.13
Sanitary Sewer Utilitv 626,843.31 574,062.04
Total Estimated Revenue 2,507,373.25 2,296,248.17
RESOLUTION NO. 2009 -135
November 23, 2009
Date Mayor
i�
ATTEST:
City Clerk
The motion for the adoption of the foregoing resolution was duly seconded by member
Dan Ryan
and upon vote being taken thereon, the following voted in favor thereof:
Tim Willson, Kay Lasman, Tim Roche, Dan Ryan, and Mark Yelich;
and the following voted against the same: none;
whereupon said resolution was declared duly passed and adopted.