HomeMy WebLinkAbout2004-129 CCRMember Kathleen Carmody. introduced the following resolution and moved
its adoption:
RESOLUTION NO. 2004-129
RESOLUTION ACCEPTING WORK PERFORMED AND AUTHORIZING FINAL
PAYMENT, IMPROVEMENT PROJECT NO. 2004-09, 2004 STREET SEAL
COATING
WHEREAS, the City of Brooklyn Center entered into a joint powers agreement with
the City of Coon Rapids to provide street seal coat maintenance work in 2004; and
WHEREAS, the 2004 Seal Coating work was awarded to Allied Blacktop Company
of Maple Grove, Minnesota pursuant to said joint powers agreement; and
WHEREAS, Allied Blacktop Company of Maple Grove, Minnesota has completed
the specified street maintenance work for Improvement Project No. 2004-09, 2004 Seal Coating.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brooklyn Center, Minnesota that:
1. It is hereby directed that final payment be made on said contract, taking the
contractor's receipt in full. The total amount to be paid to the Contractor for said
improvements shall be $103,945.56 from the Public Works Street Maintenance
Operating Budget.
2. Project costs and revenues are hereby amended as follows:
COSTS
Contract
As Approved
$104,090.95
As Final
$103,945.56
REVENUES
43220-6530 $104,090.95 $103,945.56
September 27. 2004 1./ Mt-o-
Date 4 NAyor
ATTEST: W
City Clerk
The motion for the adoption of the foregoing resolution was duly seconded by member
Kay Lasman
and upon vote being taken thereon, the following voted in favor thereof:
Myrna Kragness, Kathleen Carmody, Kay Lasman, Diane Niesen, and Bob Peppe;
and the following voted against the same: none;
whereupon said resolution was declared duly passed and adopted.