HomeMy WebLinkAbout2004-077 CCRWHEREAS, the cities of Brooklyn Park and Brooklyn Center have entered into a
Cooperative Agreement for the reconstruction of 73rd Avenue North between Penn Avenue
and Humboldt Avenue; and
WHEREAS, pursuant to the terms of the Cooperative Agreement, the contract award
to the lowest responsible bidder will be conducted by the City Council of the City of
Brooklyn Park, only upon written approval by the City Council of the City of Brooklyn
Center; and
Member Kay Lasman introduced the following resolution and moved its
adoption:
RESOLUTION NO. 2004-77
RESOLUTION AUTHORIZING AWARD OF CONTRACT, BROOKLYN
CENTER IMPROVEMENT PROJECT NO. 2004-06, 73RD AVENUE NORTH
STREET, STORM DRAINAGE, AND UTILITY IMPROVEMENTS
WHEREAS, construction bids were received, opened, and tabulated by the City of
Brooklyn Park on the 24d' day of May, 2004 for Brooklyn Park Projects ST-1415 and SS-
1416 and Brooklyn Center Improvement Project No. 2004-06. Said bids were as follows:
1
Bidder
Bid Amount
Northdale Construction
W.B. Miller, Inc.
LaTour Construction, Inc.
Dave Perkins Contracting
$ 579,274.26
$ 591,170.35
$ 604,226.22
$ 620,877.70
WHEREAS, it appears that Northdale Construction Company is the lowest
responsible bidder.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brooklyn Center, Minnesota, that:
1. The City of Brooklyn Center hereby grants written authorization to the City
of Brooklyn Park to enter into a contract with Northdale Construction
Company of Rogers, Minnesota pursuant to the Agreement for 73rd Avenue
North (Humboldt Avenue North to Penn Avenue North), Brooklyn Center
Improvement Project No. 2004-06 according to the plans and specifications
therefore approved by the City Council and on file in the office of the City
Engineer.
1
RESOLUTION NO. 2004-77
2. The estimated project costs and revenues for the Brooklyn Center portion of
the project are as follows:
COSTS Eneineer's Estimate As Amended Per Low Bid
Contract
$
358,783.59
$
354,609.61
Contingency (5%)
$
17,939.17
$
17,939.18
Administration / Legal
$
6,300.00
$
6,300.00
Engineering
$
31.400.00
$
31.400.00
Total Estimated Project Cost
$
414,422.76
$
410,248.79
REVENUES
Special Assessments $ 73,960.00
Water Utility Fund $ 65,941.50
Sanitary Sewer Utility $ 68,366.82
Storm Drainage Utility Fund $ 74,702.50
Street Construction Fund $ 131.451.94
Total Estimated Revenue $ 414,422.76
Mav 24.2004
Date
ATTEST:
City Clerk
$ 73,960.00
$ 78,011.64
$ 51,933.32
$ 78,043.48
$ 128.300.35
$ 410,248.79
Q Mayor 0
The motion for the adoption of the foregoing resolution was duly seconded by member
Kathleen Carmody
and upon vote being taken thereon, the following voted in favor thereof:
Myrna Kragness, Kathleen Carmody, Kay Lasman, Diane Niesen, and Bob Peppe;
and the following voted against the same: none;
whereupon said resolution was declared duly passed and adopted.