HomeMy WebLinkAbout2003-190 CCRMember Kay Tasman introduced the following resolution and moved its
adoption:
RESOLUTION NO. 2003-190
RESOLUTION APPROVING CHANGE ORDER NO. 1, ACCEPTING WORK
PERFORMED AND AUTHORIZING FINAL PAYMENT, IMPROVEMENT
PROJECT NO. 2002-19, CONTRACT 2002-I, SHINGLE CREEK TRAIL
RECONSTRUCTION
WHEREAS, pursuant to a written contract signed with the City of Brooklyn Center,
Minnesota, ACI Asphalt Contractors, Inc. of Maple Grove, Minnesota has completed the following
improvement in accordance with said contract:
Improvement Project No. 2002-19, Contract 2002-I, Shingle Creek Trail
Reconstruction
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brooklyn Center, Minnesota that:
1. Change Order No. 1 is hereby approved in the amount of $10,310.42.
2. It is hereby directed that final payment be made on said contract, taking
the contractor's receipt in full. The total amount to be paid for said
improvement under said contract shall be $61,172.17.
3. Project costs and revenues are hereby amended as follows:
COSTS As Approved As Final
Contract $50,861.75 $50,861.75
Contingency (10%) $5,086.18
Change Order No. 1 $10,310.42
Subtotal Construction Cost $55,947.93 $61,172.17
Admin/Legal/Eng $5,500.00 $ 1,714.14
Grant Application/Administration $1.200.00 $ 826.92
Total Project Costs $62,647.93 $63,713.23
1
RESOLUTION NO. 2003-190
REVENUES
DNR Grant Funds $28,823.97 $29,314.11
Capital Projects Fund $33,823.96 $34.399.12
Total Revenue $62,647.93 $63,713.23
December 8, 2003
Date
ATTEST:
City Clerk
44-11XA-t-d
Mayo10
The motion for the adoption of the foregoing resolution was duly seconded by member
Bob Peppe
and upon vote being taken thereon, the following voted in favor thereof:
Myrna Kragness, Kay Lasman, Diane Niesen, and Bob Peppe;
and the following voted against the same: none;
whereupon said resolution was declared duly passed and adopted.