HomeMy WebLinkAbout2001-052 CCRadoption:
RESOLUTION ACCEPTING BID AND AWARDING A CONTRACT, IMPROVEMENT
PROJECT NOS. 2001-01, 02, AND 03, CONTRACT 2001-A, GARDEN CITY NORTH
STREET, STORM DRAINAGE AND UTILITY IMPROVEMENTS
1
WHEREAS, pursuant to an advertisement for bids for Improvement Project Nos. 2001-01,
02, and 03, bids were received, opened, and tabulated by the City Clerk and Engineer on the 4th day of
April, 2001. Said bids were as follows:
Bidder
Member KaY Lasman introduced the following resolution and moved its
RESOLUTION NO. 2001-52
Arcon Construction, Inc.
Palda & Sons, Inc.
Richard Knutson, Inc.
Barbarossa & Sons, Inc
S.R. Weidema, Inc.
La Tour Contruction
Northdale Construction
Bid Amount
$2,996,354.16
$3,294,034.15
$3,342,164.20
$3,411,765.60
$3,469,527.98
$3,597,047.70
$3,599,361.73
WHEREAS, it appears that Arcon Construction is the lowest responsible bidder.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Brooklyn
Center, Minnesota that:
1. The Mayor and City Manager are hereby authorized and directed to enter into
a contract with Arcon Construction of Harris, Minnesota in the name of the
City of Brooklyn Center, for Improvement Project Nos. 2001-01, 02, and 03,
according to the plans and specifications therefore approved by the City
Council and on file in the office of the City Engineer.
2. The City Clerk is hereby authorized and directed to return forthwith to all
bidders the deposits made with their bids, except that the deposit of the
successful bidder and the next lowest bidder shall be retained until a contract is
signed.
3. The estimated project costs and revenues are as follows:
RESOLUTION NO. 2001-52
COSTS
Contract
Contingency (10%)
Feasibilitv Estimate As Amended Per Low Bid
$3,547,000.00 $2,996,354.15
354,700.00 $299,635.42
Subtotal Construction Cost
Admin/Legal/Engr.
Reforestation
Streetlights
Total Estimated Project Cost
$3,901,700.00 $3,295,989.57
$280,000.00
$312,959.90
$34,000.00
$34,000.00
$70,000.00
$70,000.00
$4,285,700.00 $3,712,949.47
REVENUES
Street Assessment
Water Fund
Storm Drainage Assessment
Storm Drainage Utility Fund
Sanitary Sewer Utility
Special Assmnt. Const. Fund
$785,368.94
$785,368.94
$654,013.20
$693, 99.02
$271,644.77
$271, 44.77
$318,847.93
$187, 98.47
$682,090.80
$617, 45.56
$1,573,734.36
$1,157,192.71
Total Estimated Revenue
April 9, 2001
Date
ATTEST: WA4&
City Clerk
$4,285,700.00 $3,712,949.47
Z.~
Mayor
The motion for the adoption of the foregoing resolution was duly seconded by member
Ed Nelson and upon vote being taken thereon, the following voted in favor thereof:
Myrna Kragness, Kay Lasman, Ed Nelson, and Bob Peppe;
and the following voted against the same: none;
whereupon said resolution was declared duly passed and adopted.