HomeMy WebLinkAbout2001-106 CCRMember Fd Nelson introduced the following resolution and moved its adoption:
RESOLUTION NO. 2001-106
RESOLUTION APPROVING CHANGE ORDER NO. 1, IMPROVEMENT PROJECT NOS.
2001-01, 02, & 03, CONTRACT 2001-A, GARDEN CITY NORTH STREET, STORM
DRAINAGE, AND UTILITY IMPROVEMENTS
WHEREAS, pursuant to a written contract signed with the City of Brooklyn Center,
Minnesota, Arcon Construction Co., Inc. is completing the following improvement in.accordance with said
contract:
Improvement Project Nos. 2001-01, 02 & 03, Contract 2001-A, Garden City North
WHEREAS, the City of Brooklyn Center wishes to add additional items pursuant to the
written contract; and
WHEREAS, the City of Brooklyn Center finds it necessary to include additional street,
utility and other related work.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Brooklyn
Center, Minnesota that:
1. Change Order No. 1 is hereby approved for additional work,
2. The total amount of Change Order No. 1 is $57,864.83. The revised contract amount
is $3,054,398.99.
3. Project costs and revenues are hereby amended as follows:
COSTS
Contract
Contingency
Change Order #1
Subtotal Construction Cost
Admin/Legal/Engr.
Reforestation
Streetlights
Total Estimated Project Cost
Contract as Bid Amended per C.O.No. 1
$2,996,354.15 $2,996,354.15
$299,635.42 241,770.59
57,864.83
$3,295,989.57 $3,295,989,57
$312,959.90 $312,959.90
$34,000.00 $34,000.00
$70,000.00 $70,000.00
$3,712,949.47 $3,712,949.47