HomeMy WebLinkAbout2010-084 CCR Member Tim Willson introduced the following resolution and moved its
adoption:
RESOLUTION NO. 2010 -84
RESOLUTION ACCEPTING BID AND AWARDING A CONTRACT,
IMPROVEMENT PROJECT NOS. 2010 -01, 02,03 AND 04, DUPONT AVENUE
STREET, STORM DRAINAGE AND UTILITY IMPROVEMENTS
WHEREAS, pursuant to an advertisement for bids for Improvement Project Nos.
2010 -01, 02, 03 and 04, bids were received, opened, and tabulated by the City Clerk and Engineer
on the 29 day of April, 2010. Said bids were as follows:
BIDDER TOTAL
Nodland Construction Co., Inc. $2,489,652.24
ASTECH Corporation $2,610,389.98
Northdale Construction Company $2,784,076.89 **
Valley Paving, Inc. $2,886,091.25
S.R. Weidema, Inc. $2,889,518.10 **
Minger Construction, Inc. $2,944,459.26 **
LaTour Construction, Inc. $2,949,046.56
Forest Lake Contracting, Inc. $3,005,463.16
Geislinger & Sons, Inc. $3,096,712.96 **
Palda and Sons, Inc. $3,164,583.57
* *Results shown above for Northdale Construction Company, S.R.Weidema, Minger Construction,
Inc., and Geislinger & Sons include minor corrections in total bid amount due to mathematical errors
on their bid forms. Corrections do not change the order of the bids.
WHEREAS, it appears that Nodland Construction Co., Inc., of Alexandria, Minnesota
is the lowest responsible bidder.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brooklyn Center, Minnesota, that:
1. The Mayor and City Manager are hereby authorized and directed to enter into
a contract with Nodland Construction Co. Inc., of Alexandria, Minnesota in
the name of the City of Brooklyn Center, for Improvement Project Nos. 2010-
01, 02, 03 and 04, according to the plans and specifications therefore
approved by the City Council and on file in the office of the City Engineer.
RESOLUTION NO. 2010 -84
2. The estimated project costs and revenues are as follows:
Amended
COSTS Estimated per Low Bid
Contract $2,737,000.00 $ 2,489,652.24
Lighting (Xcel) $ 30,000.00 $ 29,118.00
Reforestation $ 20,000.00 $ 20,000.00
Contingency $ 277,000.00 $ 277,000.00
Subtotal Construction Cost $3,064,000.00 $ 2,815,770.24
Admin/Legal /Engr. $ 395,000.00 $ 395,000.00
Total Estimated Project Cost $3,459,000.00 $ 3,210,770.24
Amended
REVENUES Estimated per Low Bid
Street Assessment $ 555,582.00 $ 558,158.00
Storm Drainage Assessment $ 76,294.00 $ 76,294.00
Sanitary Sewer Utility $ 462,000.00 $ 244,096.26
Water Utility Fund $ 346,000.00 $ 343,740.60
Storm Drainage Utility Fund $ 751,706.00 $ 699,462.00
Street Light Utility $ 37,000.00 $ 36,118.00
MSA Fund $1,230,418.00 $1,252,901.38
Total Estimated Revenue $3,459,000.00 $3,210,770.24
May 10, 2010
Date Mayor
ATTEST: J-auv T) r
City Clerk
The motion for the adoption of the foregoing resolution was duly seconded by member
Kay Lasman
and upon vote being taken thereon, the following voted in favor thereof:
Tim Willson, Kay Lasman, Tim Roche, Dan Ryan, and Mark Yelich;
and the following voted against the same: none;
whereupon said resolution was declared duly passed and adopted.