HomeMy WebLinkAbout2010-085 CCR Member Tim Roche introduced the following resolution and moved its adoption: RESOLUTION NO. 2010 -85 RESOLUTION ACCEPTING BID AND AWARDING A CONTRACT, IMPROVEMENT PROJECT NOS. 2010-05,06,07 AND 08, TWIN LAKE AREA NEIGHBORHOOD STREET, STORM DRAINAGE AND UTILITY IMPROVEMENTS WHEREAS, pursuant to an advertisement for bids for Improvement Project Nos. 2010 -05, 06, 07 and 08, bids were received, opened, and tabulated by the City Clerk and Engineer on the 29 day of April, 2010. Said bids were as follows: Bidder Total Nodland Construction Co., Inc. $3,433,246.65 ** LaTour Construction $3,460,861.20 S.R. Weidema $3,498,056.08 ** Asphalt Surface Technologies Corp. $3,646,391.01 Redstone Construction Co., Inc. $3,653,456.15 Kuechle Underground $3,808,116.01 Northwest Asphalt, Inc. $3,987,524.52 ** Northdale Construction Co., Inc. $3,992,388.56 Burschville Construction $4,096,357.75 ** Geislinger & Sons $4,303,131.50 Palda and Sons, Inc. $4,318,636.26 Thomas & Sons $4,501,783.35 ** Results shown above for Nodland Construction Co, Inc., S.R.Weidema, Northwest Asphalt and Burschville Construction include minor corrections in total bid amount due to mathematical errors on their bid forms. Corrections do not change the order of the bids. WHEREAS, it appears that Nodland Construction Co., Inc., of Alexandria, Minnesota is the lowest responsible bidder. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Brooklyn Center, Minnesota, that: I . The Mayor and City Manager are hereby authorized and directed to enter into a contract with Nodland Construction Co. Inc., of Alexandria, Minnesota in the name of the City of Brooklyn Center, for Improvement Project Nos. 2010- 05, 06, 07 and 08, according to the plans and specifications therefore approved by the City Council and on file in the office of the City Engineer. RESOLUTION NO. 2010 -85 2. The estimated project costs and revenues are as follows: Amended COSTS Estimated per Low Bid Contract $4,799,000.00 $ 3,433,246.65 Lighting $ 75,000.00 $ 44,650.00 Contingency $ 365,000.00 $ 365,000.00 Subtotal Construction Cost $5,239,000.00 $ 3,842,896.65 Admin/Legal /Engr. $ 365,000.00 $ 365,000.00 Total Estimated Project Cost $5,604,000.00 $ 4,207,896.65 Amended REVENUES Estimated per Low Bid Street Assessment $ 930,888.00 $ 930,888.00 Storm Drainage Assessment $ 306,444.00 $ 306,444.00 Sanitary Sewer Utility $1,152,000.00 $ 902,386.00 Water Utility Fund $ 828,000.00 $ 612,985.00 Storm Drainage Utility Fund $ 659,556.00 $ 394,035.70 Street Light Utility $ 87,000.00 $ 56,650.00 Street Reconstruction Fund $1,640,112.00 $1,004,507.95 Total Estimated Revenue $5,604,000.00 $4,207,896.65 i MM 10, 2010 Date Mayor ATTEST: City Clerk The motion for the adoption of the foregoing resolution was duly seconded by member Dan Ryan and upon vote being taken thereon, the following voted in favor thereof: Tim Willson, Kay Lasman, Tim Roche, Dan Ryan, and Mark Yelich; and the following voted against the same: none; whereupon said resolution was declared duly passed and adopted.