HomeMy WebLinkAbout2011-164 CCR Member Dan Ryan introduced the following resolution and moved
its adoption:
RESOLUTION NO. 2011 -164
RESOLUTION ACCEPTING WORK PERFORMED AND AUTHORIZING FINAL
PAYMENT, IMPROVEMENT PROJECT NO. 2010 -16, CONTRACT 2010 -I,
SHINGLE CREEK RESTORATION IMPROVEMENTS
WHEREAS, pursuant to a written contract signed with the City of Brooklyn Center,
Minnesota, Minnesota Native Landscapes, Inc., of Otsego, Minnesota, has completed the following
improvements in accordance with said contract:
Improvement Project No. 2010 -16, Contract 2010 4, Shingle Creek Restoration
Improvements
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brooklyn Center, Minnesota, that:
1. Final payment shall be made on Improvement Project No. 2010 -16, Contract
2010 -I, Shingle Creek Restoration Improvements, taking the contractor's
receipt in full. The total amount to be paid for said improvements under said
contract shall be $259,553.69.
2. The estimated project costs and revenues are hereby amended as follows:
COSTS As Original Award As Final
Contract $233,055.05 $236,188.19
Change Order Nos. l & 2 $ 23,365.50
Subtotal Contract $233,055.05 $259,553.69
Admin/Legal/Engr. $ 78,000.00 $ 85,111.39
Contingency $ 56,000.00
Total Project Cost $367,055.05 $344,665.08
REVENUES As Original Award As Final
Shingle Creek Watershed $127,500.00 $127,500.00
Commission
Clean Water Legacy Grant $105,237.00 $105,237.00
Hennepin County (4.5 %) $ 16,500.00 $ 15,509.93
City of Brooklyn Center (TIF 2) $117,818.05 $ 96,418.15
Total Revenue $367,055.05 $344,665.08
RESOLUTION NO. 2011 -164
December 12 2011
Date Mayor
ATTEST: J ' J' ZA /7,A
City Clerk
The motion for the adoption of the foregoing resolution was duly seconded by member
Kay Lasman
and upon vote being taken thereon, the following voted in favor thereof.
Tim Willson, Carol Kleven, Kay Lasman, and Dan Ryan;
and the following voted against the same: none;
whereupon said resolution was declared duly passed and adopted.