HomeMy WebLinkAbout2012-093 CCR Member Tim Willson introduced the following resolution and moved its
adoption:
RESOLUTION NO. 2012-93
RESOLUTION ACCEPTING WORK PERFORMED AND AUTHORIZING FINAL
PAYMENT, IMPROVEMENT PROJECT NOS. 2010-05, 06, 07 AND 08,
CONTRACT 2010-13, TWIN LAKE AREA NEIGHBORHOOD STREET AND
UTILITY IMPROVEMENTS
WHEREAS, pursuant to a written contract signed with the City of Brooklyn Center,
Minnesota,Nodland Construction Co. Inc.,of Alexandria,Minnesota has completed the following
improvements in accordance with said contract:
Improvement Project Nos.2010-05,06,07 and 08,Contract 2010-13,Twin Lake Area
Neighborhood Street and Utility Improvements
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brookl yn Center, Minnesota, that:
1. Final payment shall be made on Improvement Project Nos. 2010-05, 06, 07
and 08, 2010-13, Twin Lake Area Neighborhood Street and Utility
Improvements,taking the contractor's receipt in full The total amount to be
paid for said improvements under said contract shall be $3,385,311.41
2. The estimated construction contractual costs are hereby amended as follows:
COSTS As Original Award As Final
Contract $3,433,246.65 $3,431,553.92
Change Order Nos. 1 and 2 $ 8,925.00
Miscellaneous Charges ($ 5,167.51)
Liquidated Damages ($ 50,000.00)
Total Contract $3,433,246.65 $3,385,311.41
June 25 2012
Date Mayor
ATTEST:
City Clerk
The motion for the adoption of the foregoing resolution was duly seconded by member
Lin Myszkowski
and upon vote being taken thereon,the following voted in favor thereof:
Tim Willson, Carol Kleven, Kay Lasman, Lin Myszkowski, and Dan Ryan;
and the following voted against the same: none;
whereupon said resolution was declared duly passed and adopted.