Brooklyn Boulevard Corridor Project Phase I
(49Avenue to Bass Lake Road)
th
CITY COUNCIL WORK SESSION
October 9, 2017
Brooklyn Boulevard Corridor Project Phase I
Phase I Project Purpose:
•
The proposed reconstruction and streetscape
–
improvements will improve roadway and intersection
safety, enhance traffic operations and provide
improved bicycle and pedestrian facilities.
Project Overview
Roadway Improvements
•
51Ave & Lilac Dr Revisions
st
Frontage Road Realignment
49Ave Revisions
th
Mill &
Reconstruction
Overlay
Project Overview
Roadway Improvements
•
Curb replacement and mill and overlay from 49Avenue
th
–
to 51Avenue
st
Reconstruction of Brooklyn Boulevard from 51Avenue to
st
–
Bass Lake Road
Access modification near 51Avenue
st
–
Frontage road re-alignment near 55Avenue
th
–
Traffic signal replacement at 49Avenue, 55Avenue and
thth
–
Bass Lake Road
New traffic signal at the Trunk Highway (TH) 100 south
–
ramps
Project Overview
Bike and Pedestrian Improvements
•
Paved 10’ trail with 10’ boulevard on the west side of Brooklyn Boulevard
–
Concrete 6’ sidewalk with 10’ boulevard on the east side of Brooklyn Boulevard
–
On-street bike lane from 49Avenue to 51Avenue (connection to existing bike lanes south of 49
thstth
–
Avenue)
Pedestrian cross walk and center refuge at 51Avenue
st
–
Connection to Three Rivers Park District trail at 55Avenue
th
–
10’ Paved Trail
6’ Concrete Sidewalk
On-street
bike lanes
Trail and Sidewalk Improvements
49Avenue
th
Intersection Improvements
Conversion to 3-lane
•
section
Tightened NW radius
•
to reduce pedestrian
crossing distances
Relocation of Metro
•
Transit bus stop
Reconfiguration of
•
Xerxes Avenue
intersection
Signal reconstruction
•
including ADA, APS
and FYA
51Avenue
st
Intersection Improvements
Conversion to 3-lane
•
section south of
intersection
Center raised median
•
island for pedestrian
crossing
Closure of west leg of
•
intersection
Right in/right out entrance
•
for school and church
Addition of turn lanes (SB
•
on Brooklyn Boulevard and
on 51Avenue)
st
Bus stop consolidation
•
Proposed BRT Station
•
Lilac Drive and South TH 100
Ramp Improvements
New access to Brooklyn
•
Boulevard from Lilac
Drive
New traffic signal
•
including ADA, APS and
FYA
Removal of free right
•
turn (right turn at new
intersection)
Tighten free right
•
(vehicles travel at lower
speeds)
55Avenue Improvements
th
Signal reconstruction
•
including ADA, APS
and FYA
Removal of free right
•
turns
Realignment of
•
Frontage Road to
provide greater
intersection spacing
Relocate metro transit
•
bus stop to
intersection
Bass Lake Road (County Road 10) Improvements
Signal reconstruction
•
including ADA, APS
and FYA
Dual southbound left
•
turn lanes
Removal of free right
•
turns
Pedestrian median
•
refuge
Property Impacts
Between 49Avenue and 51
thst
–
Avenue for trail and sidewalk
construction
West of Brooklyn Boulevard at
–
55Avenue for Frontage Road re-
th
alignment
“Slivers” on east side of Brooklyn
–
Boulevard (north of TH 100)
Project Overview
Streetscaping Improvements
•
Gateway monuments at 49Avenue and Bass Lake Road
th
–
Potential gateway monuments at TH 100 south ramp
–
Project Overview
Streetscaping Improvements
•
Street lights and banner poles
–
Boulevard trees
–
Medians with trees, turf and
–
landscaping with bollards at
ends
Storm water BMPs including rain
–
gardens and infiltration swales
Existing Materials
49th Avenue Gateway -Concept A
49th Avenue Gateway -Concept A
49th Avenue Gateway -Concept B
49th Avenue Gateway -Concept B
49th Avenue Gateway -Existing
49th Avenue Gateway -Concept A
49th Avenue Gateway -Concept B
TH 100 South Bridge
TH 100 South Bridge
TH 100 North Bridge
Bass Lake Road Gateway
Bass Lake Road Gateway
Overall Project Schedule
Design and Plan Development
•
Summer 2017 -Spring 2018
–
Construction of Phase I Improvements
•
Spring 2018 -Fall 2019
–
Design and Construction of Phase II from Bass
•
Lake Road to I-694
Future improvements 2018-2021
–
Questions
Strategic Priorities:
Key Transportation Investments
•
Policy Issues:
Are the City Council’s expectations being met
•
pertaining to vision of the corridor?
Does the City Council have any comments
•
pertaining to the gateway monuments and
streetscaping?