HomeMy WebLinkAbout2018-078 CCRMember ran Rym introduced the following resolution and moved its adoption: RESOLUTION NO. 2018-78 RESOLUTION ACCEPTING BID AND AWARDING CONTRACT, IMPROVEMENT PROJECT NO. 2018-09, WATER TOWER NO. 2 AND WATER TOWER NO. 3 REHABILITATION WHEREAS, pursuant to an advertisement for bids for Improvement Project No. 2018-09, two bids were received, opened and tabulated by the City Engineer on the 16th day of March, 2018. Said bids were as follows: Bidder Schedule A Schedule B Total Base Bid TMI Coatings, Inc. $696,000 $1,391,000 $2,087,000 Classic Protective Coatings, Inc. $1,034,680 $1,432,235 $2,466,915 WHEREAS, it appears that TMI Coatings, Inc., of Saint Paul, Minnesota is the lowest responsible bidder. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Brooklyn Center, Minnesota, that 1. The Mayor and City Manager are hereby authorized and directed to enter into a contract with TMI Coatings, Inc. of Saint Paul, Minnesota, in the name of the City of Brooklyn Center, for Improvement Project No. 2018- 09, according to the plans and specifications therefore approved by the City Council and on file in the office of the City Engineer. 2. The estimated project costs and revenues are as follows: Amended COSTS Estimated per Low Bid Construction Cost $1,900,000.00 $2,087,000.00 Engineering and Administrative $ 145,000.00 $ 145,000.00 Contingency $ 100,000.00 $ 100,000.00 TOTAL $2,145,000.00 $2,332,000.00 R F V FNT TF.q Water Fund April 9, 2018 Date ATTEST: ANOAk Knyd��, City Clerk Amended Estimated per Low Bid $2,145,000.00 $2,32,000.00 Mayor The motion for the adoption of the foregoing resolution was duly seconded by member M�xgAta a tler. and upon vote being taken thereon, the following voted in favor thereof: Tim WAIsc:n, mm jaita a tier, NmI Caves, Dm Ryan and the following voted against the same: whereupon said resolution was declared duly passed and adopted.