HomeMy WebLinkAbout2019-115 CCRMember Ryan introduced the following resolution and
moved its adoption:
RESOLUTION NO. 2019-115
RESOLUTION APPROVING CHANGE ORDER NOS. 9-18, IMPROVEMENT
PROJECT NO. 2018-05, BROOKLYN BOULEVARD CORRIDOR PROJECT
PHASE 1
WHEREAS, pursuant to a written Contract signed with the City of Brooklyn
Center, Minnesota, C.S. McCrossan Construction Inc. of Maple Grove, Minnesota,
was instructed to complete additional work as itemized on Change Order Nos. 9-18 for
Improvement Project No. 2018-05, Brooklyn Boulevard Corridor Project Phase 1; and
WHEREAS, Change Order 9 in the amount of $534.28 is for MnDOT's fiber
optic interconnect between the TH 100 ramp signals; and
WHEREAS, Change Order 10 in the amount of $4,703.03 is for connecting the
existing traffic signals at Brooklyn Boulevard and 55th Avenue and at Bass Lake Road to a new
source of power due to the undergrounding of the overhead power; and
WHEREAS, Change Order 11 in the amount of -$3,000 (deduct) is for changing
rigid steel conduit to plastic conduit for the traffic signal at Brooklyn Boulevard and 49"
Avenue; and
WHEREAS, Change Order 12 in the amount of -$1,673.70 (deduct) is for failed
concrete strength tests; and
WHEREAS, Change Order 13 in the amount of $1,100 is for additional tree
removal due to an impacted root system from sidewalk installation; and
WHEREAS, Change Order 14 in the amount of $4,112.82 is for three water
services that were a different size than city records showed and for replacing a gate valve.; and
WHEREAS, Change Order 15 in the amount of $8,500 is for locating numerous
existing utilities using a vactor truck; and
WHEREAS, Change Order 16 in the amount of $2,133.45 is for additional traffic
control for a weekend closure of Brooklyn Boulevard from 49th Avenue to 51St Avenue; and
WHEREAS, Change Order 17 in the amount of $11,703.24 is for monument sign
letters that were omitted from the bid tabulation; and
WHEREAS, Change Order 18 in the amount of $3,869.19 is for repairing a water
and sanitary service that were not field located and were hit during construction; and
WHEREAS, said additional work was not included in the original Contract, but
was deemed necessary to properly complete the improvements.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brooklyn Center, Minnesota, that Change Order No. 9 through 18 in the amount of $31,982.31
for Improvement No. 2018-05 is hereby approved. The revised Contract amount is as follows:
Original Contract Amount $13,234,131.05
Change Order Nos. 1-8 $ 20,542.06
Change Order Nos. 9-18 $ 31,982.31
Revised Contract Amount $13,286,655.42
September 9, 2019
Date Mayor
ATTEST:
City Clerk
The motion for the adoption of the foregoing resolution was duly seconded by member Lawrence- Anderson
and upon vote being taken thereon, the following voted in favor thereof. Butler, Ryan, Lawrence -Anderson,
Graves, and Elliott
and the following voted against the same: None
whereupon said resolution was declared duly passed and adopted.