RESOLUTION NO.2020-07
RESOLUTION ACCEPTING BID AND AWARDING A CONTRACT,
IMPROVEMENT PROJECT NO. 2019-15, 2019 70TH AVE STORM SEWER
REHABILITATION PROJECT
WHEREAS, pursuant to an advertisement for bids for Improvement Project No.
2019-15, bids were received, opened and tabulated by the City Clerk and City Engineer on the
18th day of December, 2019. Said bids were as follows:
BIDDER TOTAL BASE BID
Engineering and Construction Innovators, Inc. $265.170.00
PCIRoads $454,037.40
Minger, Inc. $539,454.50
WHEREAS, Engineering and Construction Innovators (ECI), Inc. is the lowest
responsible bidder, based on the total base bid and;
WHEREAS, the City Engineer recommends that the contract be awarded to ECI,
Inc.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brooklyn Center, Minnesota, that
The Mayor and City Manager are hereby authorized and directed to enter
into a contract with Engineering and Construction Innovators, Inc. in the
name of the City of Brooklyn Center, for Improvement Project No. 2019-
15, according to the plans and specifications therefore approved by the
City Council and on file in the office of the City Engineer.
2. The estimated project costs and revenues are as follows:
Amended
COSTS Estimated per Low Bid
Construction Cost $243,000.00 $ 265,170.00
Engineering and Administrative $ 65,000.00 $ 70,536.00
Contingency $ 20,000.00 $ 20,000.00
TOTAL $ 328,000.00 $ 357,706.00
Amended
REVENUES Estimated per Low Bid
Storm Sewer Fund $328,000.00 $357,706.00
RESOLUTION NO.2020-07
January 13, 2020
Date
ATTEST:
City Clerk
The motion for the adoption of the foregoing resolution was duly seconded by member
Butler
and upon vote being taken thereon, the following voted in favor thereof.
Butler, Elliott, Graves, Lawrence -Anderson, Ryan
and the following voted against the same: None
whereupon said resolution was declared duly passed and adopted.