HomeMy WebLinkAbout2020-055 CCRMember Graves introduced the following resolution and moved its adoption: RESOLUTION NO.2020-055 RESOLUTION APPROVING CHANGE ORDER NOS. 19-27, IMPROVEMENT PROJECT NO. 2018-05, BROOKLYN BOULEVARD CORRIDOR PROJECT PHASE 1 WHEREAS, pursuant to a written contract signed with the City of Brooklyn Center, Minnesota, C.S. McCrossan Construction Inc. of Maple Grove, Minnesota, was instructed to complete additional work as itemized on Change Order Nos. 19-27 for Improvement Project No. 2018-05, Brooklyn Boulevard Corridor Project Phase 1, and WHEREAS, Change Order 19 in the amount of $1,222.53 is for relocating a lighting handhole which was in conflict with the footing for the ornamental fence in the northwest quadrant of 49th Avenue and Brooklyn Boulevard; and WHEREAS, Change Order 20 in the amount of $3,906.82 is for an additional rigid steel conduit and wiring to complete the traffic signal system at Brooklyn Boulevard and Bass Lake Road; and WHEREAS, .Change Order 21 in the amount of $2,424.75 is for repairing 2 water services near Brooklyn Boulevard and Bass Lake Road and for modifying Storm Structure #100 in order to avoid a conflict with an Xcel Energy duct banks and WHEREAS, .Change Order 22 in the amount of $646.95 is for re -grading the pond slope and re-laying the surrounding sod adjacent to a sanitary manhole casting which was lowered at the south infiltration basin south at Brooklyn Boulevard and 55th Avenue; and WHEREAS, Change Order 23 in the amount of-$8,887.39 (deduct) is for eliminating one metal bench at the southbound Brooklyn Boulevard bus stop at SSth Avenue, and the elimination of the Type A Bollards in the Brooklyn Boulevard median north of Bass Lake Road. The bench and bollards had been purchased specifically for this project and the elimination of the work resulted in excess materials that will be purchased from the contractor; and WHEREAS, Change Order 24 in the amount of $9,625.62 is for exposing an Xcel Energy duct bank which was in conflict with the curb and gutter near Brooklyn Boulevard and 59th Avenue, re -sequenced grading and concrete work, installing hand formed concrete curb and gutter, and providing cold weather protection for the concrete; and WHEREAS, Change Order 25 in the amount of $3,165.47 is for providing variable depth milling at pavement tie-ins and crossover locations to allow for smooth pavement transitions between existing and new pavements; and WHEREAS, Change Order 26 in the amount of $549.35 is for removing and replacing curb and gutter in the center median north of Highway 100 which was installed at the wrong elevation due to a survey error; and WHEREAS, Change Order 27 in the amount of $6,000.00 is for additional traffic control during the two Bass Lake Road closures; and WHEREAS, said additional work was not included in the original contract, but was deemed necessary to properly complete the improvements. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Brooklyn Center, Minnesota, that Change Order No. 19 through 27 in the amount of $18,654.10 for Improvement No. 2018-05 is hereby approved. The revised contract amount is as follows: Original Contract Amount $13,234,131.05 Change Order Nos. 1-8 $ 20,542.06 Change Order Nos. 9-18 $ 31,982.31 Change Order Nos. 19-27 $ 185654.10 Revised Contract Amount June 22.2020 $13,305,309.52 Mayor The motion for the adoption of the foregoing resolution was duly seconded by member Butler and upon vote being taken thereon, the following voted in favor thereof: Butler, Elliott, Graves, Lawrence -Anderson, and Ryan and the following voted against the same: None whereupon said resolution was declared duly passed and adopted.