HomeMy WebLinkAbout2021-023 CCRMember Butler introduced the following resolution and moved its adoption: RESOLUTION NO. 2021-23 RESOLUTION APPROVING CHANGE ORDER NOS. 28-34, IMPROVEMENT PROJECT NO. 2018-05, BROOKLYN BOULEVARD CORRIDOR PROJECT PHASE 1 WHEREAS, pursuant to a written contract signed with the City of Brooklyn Center, Minnesota, C.S. McCrossan Construction Inc. of Maple Grove, Minnesota, was instructed to complete additional work as itemized on Change Order Nos. 28-34 for Improvement Project No. 2018-05, Brooklyn Boulevard Corridor Project Phase 1; and WHEREAS, Change Order 28 in the amount of $1,400.00 is for additional traffic control devices used during final bituminous wearing course paving along Brooklyn Boulevard; and WHEREAS, Change Order 29 in the amount of $2,558.05 is for additional pavement markings along southbound Brooklyn Blvd south of Lilac Ave and additional crosswalk markings at 49th Avenue; and WHEREAS, Change Order 30 in the amount of-$12,680.53 (deduct) is for non- conforming concrete strength and bituminous tack material; and WHEREAS, Change Order 31 in the amount of-$130,000.00 (deduct) is for additional construction oversight during the extended construction period in 2020; and WHEREAS, Change Order 32 in the amount of $67,832.29 is for repairing vehicular accident damage to various hardscape features including bollards, lighting poles, and banner poles which occurred after the projects substantial completion; and WHEREAS, Change Order 33 in the amount of $55,097.52 is for furnishing and installing twelve (12) replacement flag poles with a banner height of 23 feet tall adjacent to turn lanes; and WHEREAS, Change Order 34 in the amount of $0.00 is for revising the Plant Establishment Period which extends the warranty for the landscape plantings beyond the one year project warranty period; and WHEREAS, said additional work was not included in the original contract, but was deemed necessary to properly complete the improvements. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Brooklyn Center, Minnesota, that Change Order No. 28 through 34 in the amount of-$15,792.67 for Improvement No. 2018-05 is hereby approved. The revised contract amount is as follows: Original Contract Amount $13,234,131.05 Change Order Nos. 1-8 $ 20,542.06 Change Order Nos. 9-18 $ 31,982.31 Change Order Nos. 19-27 $ 18,654.10 Change Order Nos. 28-34 $ -15,792.67 Revised Contract Amount 25.2021 Date ATTEST: ft&_AAMZ . City Clerk $13,289,516.85 Mayor The motion for the adoption of the foregoing resolution was duly seconded by member Lawrence -Anderson and upon vote being taken thereon, the following voted in favor thereof: Butler, Elliott, Graves, Lawrence -Anderson, Ryan and the following voted against the same: None whereupon said resolution was declared duly passed and adopted. Legend Easement Completed Easement Pending Eminent Domain - Signed Pending Mortgage Consent " Eminent Domain - Easement Negotiations On Going No Easement Required N .�*0 KN Brooklyn Boulevard Corridor Project Phase 2 (AH N'I�R AT;N6iC[NTER Easement Status 1/4/21