HomeMy WebLinkAbout2021-076 CCR Member Ryan introduced the following resolution and moved its adoption:
RESOLUTION NO. 2021-76
RESOLUTION ACCEPTING WORK PERFORMED AND AUTHORIZING
FINAL PAYMENT, IMPROVEMENT PROJECT NO. 2020-07, WATER
TOWER NO. 1 REHABILITATION
WHEREAS, pursuant to a written contract signed with the City of Brooklyn
Center, Minnesota, Osseo Construction Company has completed Improvement Project No. 2020-
07, Water Tower No. 1 Rehabilitation.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Brooklyn Center, Minnesota, that
1. Final payment shall be made on Improvement Project Nos. 2020-07,
Water Tower No. 1 Rehabilitation, taking the contractor's receipt in full.
The total amount to be paid for said improvements under said contract
shall be $699,615.00.
2. The estimated project costs and revenues are hereby amended as follows:
COSTS As Awarded As Final
Construction Cost $ 707,950.00 $699,615.00
Engineering and Administrative $ 87,000.00 $ 85,241.00
Contin ency $ 55,050.00 $ 6,108.00
TOTAL $ 850,000.00 $790,964.00
REVENUES As Awarded As Final
Water Fund $ 850,000.00 $790,964.00
June 14, 2021
Date Mayor
ATTEST: ��,� ��lI�1/�rt( .�
City Clerk
The motion for the adoption of the foregoing resolution was duly seconded by member
Elliott
and upon vote being taken thereon, the following voted in favor thereof:
Elliott, Graves, and Ryan
and the following voted against the same: None
whereupon said resolution was declared duly passed and adopted.